Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 98

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 98 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Spectrum Solar II
Solar
3.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2018target 2022
Solar project AB1-145, Camden County
Solar
3.0 MWWithdrawn / abandoned Camden, NJPJM Oct 2015target 2016
Solar project AC1-228, Dorchester County
Solar
3.0 MWWithdrawn / abandoned Dorchester, MDPJM Oct 2016target 2018
Solar project AF2-093, Montour County
Solar
3.0 MWWithdrawn / abandoned Montour, PAPJM Jan 2020target 2021
LK-Justus
Solar + storage
3.0 MWWithdrawn / abandoned Lackawanna, PAPJM Mar 2020target 2023
Solar project AB2-035, Pitt County
Solar
3.0 MWWithdrawn / abandoned Pitt, NCPJM Feb 2016target 2016
Fairfield at Howell Solar Farm
Solar
3.0 MWWithdrawn / abandoned Monmouth, NJPJM Aug 2010target 2014
LH Church
Solar + storage
3.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2024
Solar project AG2-139, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Feb 2021target 2022
Solar project AH1-021, Berks County
Solar
3.0 MWWithdrawn / abandoned Berks, PAPJM May 2021target 2022
Other project AB1-186
Other
3.0 MWWithdrawn / abandoned PJM Nov 2015target 2016
Solar project AH1-286, Preston County
Solar
3.0 MWWithdrawn / abandoned Preston, WVPJM Sep 2021target 2023
Solar project AC2-005, Dorchester County
Solar
3.0 MWWithdrawn / abandoned Dorchester, MDPJM Nov 2016target 2018
Solar project AE2-198, Mercer County
Solar
2.8 MWWithdrawn / abandoned Mercer, NJPJM Mar 2019
Solar + storage project AE2-099, Burlington County
Solar + storage
2.8 MWWithdrawn / abandoned Burlington, NJPJM Feb 2019target 2020
Solar project AD1-153, Prince George's County
Solar
2.8 MWWithdrawn / abandoned Prince George's, MDPJM Sep 2017target 2018
Solar project AE2-096, Hunterdon County
Solar
2.8 MWWithdrawn / abandoned Hunterdon, NJPJM Feb 2019target 2020
Solar project AG2-155, Lycoming County
Solar
2.8 MWWithdrawn / abandoned Lycoming, PAPJM Feb 2021target 2022
Solar project X1-107, Sussex County
Solar
2.8 MWWithdrawn / abandoned Sussex, NJPJM Apr 2011target 2012
Essex SP
Gas
2.8 MWWithdrawn / abandoned Essex, NJPJM Jun 2009target 2010
Solar project AF2-202, Salem County
Solar
2.7 MWWithdrawn / abandoned Salem, NJPJM Mar 2020target 2021
Other project V2-002, Blair County
Other
2.7 MWWithdrawn / abandoned Blair, PAPJM May 2009target 2010
Levittown 13kV
Solar
2.6 MWWithdrawn / abandoned Burlington, NJPJM Aug 2017target 2019
Solar project AE2-165, Passaic County
Solar
2.6 MWWithdrawn / abandoned Passaic, NJPJM Mar 2019target 2020
Beltzville Hydro Dam
Hydro
2.6 MWWithdrawn / abandoned Carbon, PAPJM Jun 2008target 2014
Pattenburg Quarry Solar Farm
Solar
2.6 MWWithdrawn / abandoned Hunterdon, NJPJM Dec 2010target 2014
Solar project W3-153, Montgomery County
Solar
2.6 MWWithdrawn / abandoned Montgomery, PAPJM Oct 2010target 2011
Solar project AB1-072, Washington County
Solar
2.5 MWWithdrawn / abandoned Washington, MDPJM Sep 2015target 2016
Solar project AF2-058, Cumberland County
Solar
2.5 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2020target 2021
Solar project AG2-087, Camden County
Solar
2.5 MWWithdrawn / abandoned Camden, NJPJM Jan 2021target 2022
Solar + storage project AE2-088, Gloucester County
Solar + storage
2.5 MWWithdrawn / abandoned Gloucester, NJPJM Feb 2019target 2020
Onshore wind project P18, Lee County
Onshore wind
2.5 MWWithdrawn / abandoned Lee, ILPJM Oct 2005target 2007
Solar project X1-104, Hunterdon County
Solar
2.5 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2011target 2012
Solar project W3-152, Warren County
Solar
2.5 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2011
Solar + storage project AE2-145, Burlington County
Solar + storage
2.5 MWWithdrawn / abandoned Burlington, NJPJM Mar 2019target 2020
Solar project W2-041, Atlantic County
Solar
2.5 MWWithdrawn / abandoned Atlantic, NJPJM Jun 2010target 2011
Meadow Road Solar
Solar
2.5 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2016target 2018
Solar project W3-096, Montgomery County
Solar
2.5 MWWithdrawn / abandoned Montgomery, PAPJM Oct 2010target 2011
North Union CSG 1
Solar
2.5 MWWithdrawn / abandoned Fayette, PAPJM Sep 2020target 2022
Solar project AC1-138, Boone County
Solar
2.5 MWWithdrawn / abandoned Boone, KYPJM Oct 2016target 2017
Solar project W1-091, Camden County
Solar
2.5 MWWithdrawn / abandoned Camden, NJPJM Apr 2010target 2011
Reeve's Station North
Solar
2.4 MWWithdrawn / abandoned Burlington, NJPJM Dec 2010target 2014
Solar project AE2-337, Prince George's County
Solar
2.4 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2019target 2020
Sight & Sound Theaters
Other
2.4 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2010target 2012
Solar project X2-015, Burlington County
Solar
2.3 MWWithdrawn / abandoned Burlington, NJPJM May 2011target 2011
Onshore wind project W4-071, Somerset County
Onshore wind
2.3 MWWithdrawn / abandoned Somerset, PAPJM Jan 2011target 2012
Solar project AE2-100, Bergen County
Solar
2.3 MWWithdrawn / abandoned Bergen, NJPJM Feb 2019target 2020
Solar project X2-003, Bergen County
Solar
2.1 MWWithdrawn / abandoned Bergen, NJPJM May 2011target 2012
Other project Q66, Will County
Other
2.1 MWWithdrawn / abandoned Will, ILPJM Jul 2006target 2007
Solar + storage project AE2-095, Mercer County
Solar + storage
2.1 MWWithdrawn / abandoned Mercer, NJPJM Feb 2019target 2020
Page 98 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)