United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

SOLAR Β· PJM

Solar project AE2-198, Mercer County

Solar project AE2-198, Mercer County is a 2.8 MW solar request withdrawn in the PJM interconnection queue, in Mercer County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-198
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Location
Mercer County, New Jersey
Technology
Solar: 2.8 MW
Total requested
2.8 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
19 March 2019
Withdrawn
April 2019

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem