Other project AB1-186

Other project AB1-186 is a 3.0 MW other request withdrawn in the PJM interconnection queue, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB1-186
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
REDLION 34.5 KV REDLINFC-KENT 13 KV DOVER2CT
Technology
Other: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: System Impact Study
Queue status
Withdrawn
Entered queue
3 November 2015
Proposed online date
June 2016
Withdrawn
November 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem