United States › Grid › Interconnection queues › New Jersey
SOLAR · PJMReeve's Station North
Reeve's Station North is a 2.4 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2010 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W4-029
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Connection point (POI)
- Medford 13kV
- Location
- Burlington County, New Jersey
- Technology
- Solar: 2.4 MW
- Total requested
- 2.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 17 December 2010
- Proposed online date
- December 2014
- Withdrawn
- October 2018
Location
Marker shows the centre of Burlington County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Burlington County
- NaesBattery storage · 5.0 MW · agreement signed
- Battery storage project AH2-127, Burlington CountyBattery storage · 18.0 MW · in study
- NJ Land Phase IISolar · 10.0 MW · suspended
- BurlingtonGas · 168 MW · built
- North Hanover Solar FarmSolar · 17.0 MW · built
- Burlington #10Gas · 16.0 MW · built
- Cedar LaneSolar · 15.0 MW · built
- Dix Solar FarmSolar · 13.0 MW · built
- Reeves Station Road SolarSolar · 11.0 MW · built
- Taylors Lane SolarSolar · 10.0 MW · built
- Burlington (L&D Solar) 26kVSolar · 10.0 MW · built
- Perez SolarSolar · 8.8 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem