| Project | Capacity | Status |
|---|---|---|
| Solar project 22333, Onslow County Solar ยท Masked |
185 MW | Withdrawn / abandoned |
| Half Moon Solar (supsended) Solar ยท Nextera |
181 MW | Withdrawn / abandoned |
| Solar project AE1-235, Dinwiddie County Solar |
180 MW | Withdrawn / abandoned |
| Solar project 58, Douglas County Solar |
176 MW | Withdrawn / abandoned |
| Solar project GEN-2018-101, Bates County Solar |
175 MW | Withdrawn / abandoned |
| Solar project GEN-2018-081, Lamb County Solar |
175 MW | Withdrawn / abandoned |
| Erie-Wyoming County Solar Solar + storage ยท ConnectGen Erie-Wyoming LLC |
175 MW | Withdrawn / abandoned |
| Dillon Gulch Wind Onshore wind ยท AES |
175 MW | Withdrawn / abandoned |
| Solar + storage project Company JN, Churchill County Solar + storage |
175 MW | Withdrawn / abandoned |
| Onshore wind project AD2-191, Seneca County Onshore wind |
170 MW | Withdrawn / abandoned |
| Gas project IA-PNM-2018-07, Valencia County Gas |
170 MW | Withdrawn / abandoned |
| Solar project J1089, Shiawassee County Solar |
170 MW | Withdrawn / abandoned |
| Solar project IC-753, Turner County Solar |
170 MW | Withdrawn / abandoned |
| Solar + storage project 2018-G5 Solar + storage |
170 MW | Withdrawn / abandoned |
| Alder Creek Solar Solar ยท Alder Creek Solar, LLC |
165 MW | Withdrawn / abandoned |
| Dusky Solar Solar ยท Cypress Creek Renewables |
165 MW | Withdrawn / abandoned |
| Tepona Off-Shore Wind Offshore wind |
162 MW | Withdrawn / abandoned |
| Solar project IC-707, Jasper County Solar |
160 MW | Withdrawn / abandoned |
| Offshore wind project AD2-212, Worcester County Offshore wind |
160 MW | Withdrawn / abandoned |
| Chaumont Solar Solar ยท Oya Solar NY, LP |
160 MW | Withdrawn / abandoned |
| Solar + storage project 1073, Juab County Solar + storage |
160 MW | Withdrawn / abandoned |
| Solar + storage project 1074, Utah County Solar + storage |
160 MW | Withdrawn / abandoned |
| Stargaze Solar BESS Solar |
154 MW | Withdrawn / abandoned |
| Limon Energy Park Solar + storage |
153 MW | Withdrawn / abandoned |
| Solar project IC-749, Brantley County Solar |
153 MW | Withdrawn / abandoned |
| Cowboy Solar Solar ยท AP Solar Holdings LLC |
153 MW | Withdrawn / abandoned |
| Timberwolf POI A Solar Solar ยท CED Crane Solar 2, LLC |
152 MW | Withdrawn / abandoned |
| Offshore wind project AE1-118, Sussex County Offshore wind |
152 MW | Withdrawn / abandoned |
| Offshore wind project AE1-117, Sussex County Offshore wind |
152 MW | Withdrawn / abandoned |
| Onshore wind project J1187, Mercer County Onshore wind |
152 MW | Withdrawn / abandoned |
| Falcon Energy Center Battery storage |
151 MW | Withdrawn / abandoned |
| Solar project J1112, Kosciusko County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project J1031, Henry County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project GEN-2018-117, Roger Mills County Solar |
150 MW | Withdrawn / abandoned |
| Altajac Gas ยท Alta Power |
150 MW | Withdrawn / abandoned |
| Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Solar + storage project AD2-168, Winnebago County Solar + storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project AD2-155, Kankakee County Onshore wind |
150 MW | Withdrawn / abandoned |
| Battery storage project 59, Pierce County Battery storage |
150 MW | Withdrawn / abandoned |
| Solar project 18-05021, Weld County Solar |
150 MW | Withdrawn / abandoned |
| Solar + storage project IC-739, Macon County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project Company IO, Humboldt County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project AD2-148, Dekalb County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project J1091, Craighead County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project J1018, Miami County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project AD2-140, Will County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project AE1-168, Nottoway County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project AD2-196, Luzerne County Onshore wind |
150 MW | Withdrawn / abandoned |
| Avocet Gas ยท Alta Power Lufkin Acovet |
150 MW | Withdrawn / abandoned |
| Solar + storage project AE1-023, Winnebago County Solar + storage |
150 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)306 ยท 50.5 GW
- PJM (Mid-Atlantic, Midwest)311 ยท 46.6 GW
- MISO (Midcontinent)165 ยท 28.2 GW
- Southeast (non-ISO utilities)248 ยท 28.2 GW
- CAISO (California)67 ยท 21.7 GW
- SPP (Southwest Power Pool)92 ยท 16.8 GW
- ERCOT (Texas)77 ยท 15.0 GW
- NYISO (New York)74 ยท 11.2 GW
- ISO-NE (New England)84 ยท 8,151 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)