United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

SOLAR Β· WEST

Solar project Company IO, Humboldt County

Solar project Company IO, Humboldt County is a 150 MW solar request withdrawn in the West interconnection queue, in Humboldt County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company IO
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Humboldt County, Nevada
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
30 March 2018
Proposed online date
October 2020

Location

Marker shows the centre of Humboldt County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Humboldt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem