🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in SPP (Southwest Power Pool) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,846382.9 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,846 requests · page 9 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-157, Allen County
Onshore wind
252 MWWithdrawn / abandoned Allen, KSSPP Nov 20162025
Onshore wind project GEN-2016-158, Allen County
Onshore wind
252 MWWithdrawn / abandoned Allen, KSSPP Nov 20162025
Onshore wind project GEN-2017-147, Johnson County
Onshore wind
252 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2016-162, Marion County
Onshore wind
252 MWWithdrawn / abandoned Marion, KSSPP Nov 20162024
Solar project GEN-2018-058, Leavenworth County
Solar
252 MWWithdrawn / abandoned Leavenworth, KSSPP May 20182024
Solar project GEN-2018-059, Leavenworth County
Solar
252 MWWithdrawn / abandoned Leavenworth, KSSPP May 20182024
Onshore wind project GEN-2017-126, Jackson County
Onshore wind
252 MWWithdrawn / abandoned Jackson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2017-125, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Nov 2017target 2027
Onshore wind project GEN-2017-124, Jackson County
Onshore wind
252 MWWithdrawn / abandoned Jackson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2020-071, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Apr 20202024
Onshore wind project GEN-2017-139, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2017-127, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Nov 2017target 2020
Onshore wind project GEN-2017-152, Mcclain County
Onshore wind
252 MWWithdrawn / abandoned Mcclain, OKSPP Nov 2017target 2027
Onshore wind project GEN-2023-134, Hughes County
Onshore wind
252 MWWithdrawn / abandoned Hughes, OKSPP Oct 2023target 2026
Onshore wind project GEN-2018-008, Mcintosh County
Onshore wind
252 MWWithdrawn / abandoned Mcintosh, NDSPP Apr 20182025
Onshore wind project GEN-2016-163, Harvey County
Onshore wind
252 MWWithdrawn / abandoned Harvey, KSSPP Nov 20162024
Onshore wind project GEN-2020-052, Labette County
Onshore wind
251 MWWithdrawn / abandoned Labette, KSSPP Apr 20202025
Onshore wind project GEN-2016-062, Andrews County
Onshore wind
251 MWWithdrawn / abandoned Andrews, TXSPP Mar 2016target 2018
Onshore wind project GEN-2015-010, Roosevelt County
Onshore wind
251 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2015target 2017
Onshore wind project GEN-2011-049, Beckham County
Onshore wind
251 MWWithdrawn / abandoned Beckham, OKSPP Sep 20112020
Onshore wind project GEN-2008-029, Ellis County
Onshore wind
251 MWWithdrawn / abandoned Ellis, OKSPP Apr 2008target 2010
Onshore wind project GEN-2015-060, Ellis County
Onshore wind
251 MWWithdrawn / abandoned Ellis, OKSPP Oct 2015target 2021
Onshore wind project GEN-2011-007, Canadian County
Onshore wind
250 MWWithdrawn / abandoned Canadian, OKSPP Mar 2011target 2011
Onshore wind project GEN-2024-152, Cheyenne County
Onshore wind
250 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2023-133, Custer County
Onshore wind
250 MWWithdrawn / abandoned Custer, NESPP Oct 2023target 2030
Coal project GEN-2001-029N1, Adams County
Coal
250 MWWithdrawn / abandoned Adams, NESPP Sep 2001
Solar project GEN-2024-357, Roosevelt County
Solar
250 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2029
Battery storage project GEN-2022-133, Potter County
Battery storage
250 MWWithdrawn / abandoned Potter, TXSPP Feb 2023target 2027
Onshore wind project GEN-2018-083, Madison County
Onshore wind
250 MWWithdrawn / abandoned Madison, NESPP Nov 2018target 2027
Solar + storage project GEN-2022-029, Lea County
Solar + storage
250 MWWithdrawn / abandoned Lea, NMSPP Jun 2022target 2027
Solar project GEN-2022-167, Tulsa County
Solar
250 MWWithdrawn / abandoned Tulsa, OKSPP Feb 2023target 2028
Onshore wind project GEN-2016-098, Harper County
Onshore wind
250 MWWithdrawn / abandoned Harper, OKSPP Nov 2016target 2020
Onshore wind project GEN-2023-047, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Solar project GEN-2024-270, Tulsa County
Solar
250 MWWithdrawn / abandoned Tulsa, OKSPP Mar 2025target 2030
Onshore wind project GEN-2024-196, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Onshore wind project GEN-2023-094, Morton County
Onshore wind
250 MWWithdrawn / abandoned Morton, KSSPP Oct 2023target 2028
Battery storage project GEN-2023-009, Haskell County
Battery storage
250 MWWithdrawn / abandoned Haskell, OKSPP Oct 2023target 2028
Solar + storage project GEN-2021-004, Carter County
Solar + storage
250 MWWithdrawn / abandoned Carter, OKSPP Apr 2021target 2027
Onshore wind project GEN-2022-216, Castro County
Onshore wind
250 MWWithdrawn / abandoned Castro, TXSPP Mar 2023target 2027
Solar + storage project GEN-2020-059, Lea County
Solar + storage
250 MWWithdrawn / abandoned Lea, NMSPP Apr 2020target 2027
Solar + storage project GEN-2024-263, Lea County
Solar + storage
250 MWWithdrawn / abandoned Lea, NMSPP Mar 2025target 2029
Onshore wind project GEN-2016-099, Parmer County
Onshore wind
250 MWWithdrawn / abandoned Parmer, TXSPP Nov 2016target 2020
Onshore wind project GEN-2022-205, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2023target 2027
Onshore wind project GEN-2013-024, Cherry County
Onshore wind
250 MWWithdrawn / abandoned Cherry, NESPP Sep 2013target 2018
Gas project GEN-2011-052, Jackson County
Gas
250 MWWithdrawn / abandoned Jackson, MOSPP Sep 2011target 2014
Battery storage project GEN-2023-073, Butler County
Battery storage
250 MWWithdrawn / abandoned Butler, KSSPP Oct 2023target 2027
Onshore wind project GEN-2022-122, Oldham County
Onshore wind
250 MWWithdrawn / abandoned Oldham, TXSPP Feb 2023target 2027
Solar project GEN-2018-126, Johnson County
Solar
250 MWWithdrawn / abandoned Johnson, KSSPP Nov 2018target 2021
Battery storage project GEN-2023-235, Benton County
Battery storage
250 MWWithdrawn / abandoned Benton, ARSPP Oct 20232025
Onshore wind project GEN-2023-046, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Page 9 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)