Onshore wind project GEN-2016-098, Harper County

Onshore wind project GEN-2016-098, Harper County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Harper County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedAug 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-098
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Badger-Woodward EHV Dbl Ckt 345kV
Location
Harper County, Oklahoma
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
7 November 2016
Proposed online date
October 2020
Withdrawn
August 2018

Location

Marker shows the centre of Harper County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Harper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem