Requests shown51469.7 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

514 requests · page 9 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G375, Cottonwood County
Onshore wind
20.0 MWOperating Cottonwood, MNMISO Nov 20032005
Onshore wind project G536, Jackson County
Onshore wind
20.0 MWOperating Jackson, MNMISO Jul 20052009
Onshore wind project G532, Cottonwood County
Onshore wind
20.0 MWOperating Cottonwood, MNMISO Jul 20052006
Onshore wind project G474, Grant County
Onshore wind
20.0 MWOperating Grant, MNMISO Oct 20042005
Onshore wind project J289, Madison County
Onshore wind
20.0 MWOperating Madison, IAMISO Jul 20132013
Coal project G170, Washington County
Coal
20.0 MWOperating Washington, MNMISO Jan 20022006
Solar project J1142, St. James Parish County
Solar
20.0 MWOperating St. James Parish, LAMISO Mar 20182020
Onshore wind project J201, Bay County
Onshore wind
20.0 MWOperating Bay, MIMISO Feb 20112013
Battery storage project J401, Marion County
Battery storage
20.0 MWOperating Marion, INMISO Nov 20142016
Onshore wind project G685, Meeker County
Onshore wind
20.0 MWOperating Meeker, MNMISO Oct 20062008
Onshore wind project G330, Mower County
Onshore wind
19.0 MWOperating Mower, MNMISO Apr 20032003
Onshore wind project G291, Lamoure County
Onshore wind
19.0 MWOperating Lamoure, NDMISO Feb 20032006
Onshore wind project G242, Dodge County
Onshore wind
19.0 MWOperating Dodge, MNMISO Aug 20022008
Other project G327, Marinette County
Other
19.0 MWOperating Marinette, WIMISO Mar 20032003
Coal project G806, Montgomery County
Coal
19.0 MWOperating Montgomery, ILMISO Jun 20072016
Other project G324, Oneida County
Other
19.0 MWOperating Oneida, WIMISO Mar 20032003
Nuclear project G433, Goodhue County
Nuclear
19.0 MWOperating Goodhue, MNMISO Jun 20042005
Nuclear project G434, Goodhue County
Nuclear
19.0 MWOperating Goodhue, MNMISO Jun 20042006
Onshore wind project G566d, Missaukee County
Onshore wind
18.0 MWOperating Missaukee, MIMISO Oct 20062008
Other project G641, Cook County
Other
18.0 MWOperating Cook, MNMISO May 20062008
Gas project G342, Baraga County
Gas
18.0 MWOperating Baraga, MIMISO Jun 20032003
Solar project J453, Martin County
Solar
17.3 MWOperating Martin, INMISO May 20152019
Coal project G535, Fulton County
Coal
16.0 MWOperating Fulton, ILMISO Jul 20052008
Other project G325, Oneida County
Other
16.0 MWOperating Oneida, WIMISO Mar 20032003
Other project G344, Dickinson County
Other
15.0 MWOperating Dickinson, MIMISO Jun 2003
Gas project E002, Pointe Coupee Parish County
Gas
15.0 MWOperating Pointe Coupee Parish, LAMISO Sep 20132015
Hydro project G547, Miller County
Hydro
15.0 MWOperating Miller, MOMISO Sep 20052005
Other project G347
Other
15.0 MWOperating MIMISO Jun 2003
Other project G417, Scott County
Other
15.0 MWOperating Scott, MNMISO Mar 20042006
Hydro project J145, Miller County
Hydro
14.0 MWOperating Miller, MOMISO Jun 20102004
Onshore wind project G171, Dodge County
Onshore wind
14.0 MWOperating Dodge, MNMISO Jan 2002
Onshore wind project G530, Greene County
Onshore wind
14.0 MWOperating Greene, IAMISO Jun 20052006
Nuclear project G725, Wright County
Nuclear
13.0 MWOperating Wright, MNMISO Jan 20072008
Onshore wind project G667, Jackson County
Onshore wind
13.0 MWOperating Jackson, MNMISO Aug 20062007
Other project J242, Macomb County
Other
12.8 MWOperating Macomb, MIMISO May 20122016
Other project J025, Macomb County
Other
12.8 MWOperating Macomb, MIMISO Feb 20092010
Onshore wind project J794, Gratiot County
Onshore wind
12.5 MWOperating Gratiot, MIMISO Jun 20172018
Onshore wind project G253, Rock County
Onshore wind
12.0 MWOperating Rock, MNMISO Sep 20022002
Onshore wind project G408, Mchenry County
Onshore wind
12.0 MWOperating Mchenry, NDMISO Mar 20042005
Onshore wind project R49, Calhoun County
Onshore wind
12.0 MWOperating Calhoun, IAMISO Jan 20082010
Other project G322, Brown County
Other
10.0 MWOperating Brown, WIMISO Mar 20032010
Other project G723, Morton County
Other
10.0 MWOperating Morton, NDMISO Dec 20062008
Onshore wind project G272, Murray County
Onshore wind
10.0 MWOperating Murray, MNMISO Dec 20022004
Onshore wind project G252, Murray County
Onshore wind
10.0 MWOperating Murray, MNMISO May 20022005
Nuclear project G428, Wright County
Nuclear
10.0 MWOperating Wright, MNMISO May 20042005
Coal project J1146, Mississippi County
Coal
10.0 MWOperating Mississippi, ARMISO Mar 20182020
Onshore wind project J558, Pipestone County
Onshore wind
9.2 MWOperating Pipestone, MNMISO Apr 20162017
Onshore wind project G285, Pipestone County
Onshore wind
9.0 MWOperating Pipestone, MNMISO Jul 20012004
Onshore wind project G310, Cerro Gordo County
Onshore wind
8.0 MWOperating Cerro Gordo, IAMISO Mar 20032005
Other project G741, Martin County
Other
8.0 MWOperating Martin, MNMISO Feb 20072011
Page 9 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)