United States › Grid › Interconnection queues › Missouri
HYDRO · MISOHydro project J145, Miller County
Hydro project J145, Miller County is a 14.0 MW hydro request built and operating in the MISO interconnection queue, in Miller County, Missouri.
Request details
- Queue ID
- J145
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Osage Power Plant
- Location
- Miller County, Missouri
- Technology
- Hydro: 14.0 MW
- Total requested
- 14.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 25 June 2010
- Agreement signed
- 28 June 2012
- Proposed online date
- June 2004
- Came online
- June 2004
Location
Marker shows the centre of Miller County; the queue data does not give exact sites.
Other requests in Miller County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem