United States › Grid › Interconnection queues › Georgia

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Georgia — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown510106.6 GW
Active in queue46.5 GW204 requests
Agreement signed16.6 GW57 requests
Withdrawn510106.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

510 requests · page 8 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-632, Pierce County
Solar
69.9 MWWithdrawn / abandoned Pierce, GASoutheast Apr 2017
Solar project IC-591, Twiggs County
Solar
68.5 MWWithdrawn / abandoned Twiggs, GASoutheast Jan 2017
Solar project IC-502, Dodge County
Solar
68.5 MWWithdrawn / abandoned Dodge, GASoutheast Sep 2016
Solar project IC-512, Wilcox County
Solar
68.5 MWWithdrawn / abandoned Wilcox, GASoutheast Oct 2016
Solar project IC-483, Tift County
Solar
68.4 MWWithdrawn / abandoned Tift, GASoutheast Aug 2016
Solar project IC-904, Coffee County
Solar
64.0 MWWithdrawn / abandoned Coffee, GASoutheast Sep 2020
Solar project IC-380, Twiggs County
Solar
60.0 MWWithdrawn / abandoned Twiggs, GASoutheast May 2014
Solar project IC-538, Berrien County
Solar
60.0 MWWithdrawn / abandoned Berrien, GASoutheast Nov 2016
Solar project IC-615, Jefferson County
Solar
60.0 MWWithdrawn / abandoned Jefferson, GASoutheast Mar 2017
Solar project IC-597, Sumter County
Solar
60.0 MWWithdrawn / abandoned Sumter, GASoutheast Feb 2017
Solar project IC-637, Hancock County
Solar
60.0 MWWithdrawn / abandoned Hancock, GASoutheast Apr 2017
Solar project IC-636, Jasper County
Solar
60.0 MWWithdrawn / abandoned Jasper, GASoutheast Apr 2017
Solar project IC-466, Sumter County
Solar
60.0 MWWithdrawn / abandoned Sumter, GASoutheast Jul 2016
Solar project IC-603, Clay County
Solar
60.0 MWWithdrawn / abandoned Clay, GASoutheast Mar 2017
Solar project IC-625, Bulloch County
Solar
58.8 MWWithdrawn / abandoned Bulloch, GASoutheast Apr 2017
Solar project IC-554, Coffee County
Solar
57.0 MWWithdrawn / abandoned Coffee, GASoutheast Dec 2016
Solar project IC-449, Terrell County
Solar
56.0 MWWithdrawn / abandoned Terrell, GASoutheast Mar 2016
Other project IC-246, Troup County
Other
55.0 MWWithdrawn / abandoned Troup, GASoutheast Jan 2011
Solar project IC-471, Decatur County
Solar
52.0 MWWithdrawn / abandoned Decatur, GASoutheast Jul 2016
Solar project IC-551, Tattnall County
Solar
52.0 MWWithdrawn / abandoned Tattnall, GASoutheast Dec 2016
Solar project IC-588, Lowndes County
Solar
52.0 MWWithdrawn / abandoned Lowndes, GASoutheast Jan 2017
Solar project IC-713, Macon County
Solar
52.0 MWWithdrawn / abandoned Macon, GASoutheast Jun 2018
Solar project IC-492, Houston County
Solar
50.5 MWWithdrawn / abandoned Houston, GASoutheast Sep 2016
Solar project IC-321, Wayne County
Solar
50.0 MWWithdrawn / abandoned Wayne, GASoutheast Oct 2013
Solar project IC-324, Early County
Solar
50.0 MWWithdrawn / abandoned Early, GASoutheast Nov 2013
Solar project IC-778, Dodge County
Solar
50.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2019
Battery storage project IC-1155, Chatham County
Battery storage
50.0 MWWithdrawn / abandoned Chatham, GASoutheast Jul 2023target 2025
Solar project IC-322, Wilkinson County
Solar
50.0 MWWithdrawn / abandoned Wilkinson, GASoutheast Oct 2013
Solar project IC-328, Seminole County
Solar
50.0 MWWithdrawn / abandoned Seminole, GASoutheast Dec 2013
Solar project IC-320, Wayne County
Solar
50.0 MWWithdrawn / abandoned Wayne, GASoutheast Oct 2013
Solar project 308, Murray County
Solar
50.0 MWWithdrawn / abandoned Murray, GASoutheast Jan 2017
Solar project IC-327, Decatur County
Solar
50.0 MWWithdrawn / abandoned Decatur, GASoutheast Dec 2013
Solar project IC-377, Tattnall County
Solar
50.0 MWWithdrawn / abandoned Tattnall, GASoutheast May 2014
Solar project IC-456, Twiggs County
Solar
50.0 MWWithdrawn / abandoned Twiggs, GASoutheast Apr 2016
Solar project IC-1095, Bartow County
Solar
50.0 MWWithdrawn / abandoned Bartow, GASoutheast Nov 2022target 2026
Solar project IC-564, Peach County
Solar
49.9 MWWithdrawn / abandoned Peach, GASoutheast Dec 2016
Solar project IC-370, Clinch County
Solar
49.9 MWWithdrawn / abandoned Clinch, GASoutheast Apr 2014
Solar project IC-590, Glascock County
Solar
48.0 MWWithdrawn / abandoned Glascock, GASoutheast Jan 2017
Solar project IC-578, Early County
Solar
46.0 MWWithdrawn / abandoned Early, GASoutheast Jan 2017
Solar project IC-642, Turner County
Solar
45.0 MWWithdrawn / abandoned Turner, GASoutheast May 2017
Solar project IC-332, Jenkins County
Solar
43.0 MWWithdrawn / abandoned Jenkins, GASoutheast Jan 2014
Solar project IC-513, Dodge County
Solar
42.5 MWWithdrawn / abandoned Dodge, GASoutheast Oct 2016
Solar project IC-565, Bulloch County
Solar
40.1 MWWithdrawn / abandoned Bulloch, GASoutheast Dec 2016
Solar project IC-614, Colquitt County
Solar
40.0 MWWithdrawn / abandoned Colquitt, GASoutheast Mar 2017
Solar project IC-514, Oconee County
Solar
40.0 MWWithdrawn / abandoned Oconee, GASoutheast Oct 2016
Solar project IC-543, Laurens County
Solar
40.0 MWWithdrawn / abandoned Laurens, GASoutheast Nov 2016
Solar project IC-613, Jefferson County
Solar
40.0 MWWithdrawn / abandoned Jefferson, GASoutheast Mar 2017
Solar project IC-761, Elbert County
Solar
40.0 MWWithdrawn / abandoned Elbert, GASoutheast Dec 2018
Solar project IC-601, Tattnall County
Solar
40.0 MWWithdrawn / abandoned Tattnall, GASoutheast Feb 2017
Solar project IC-541, Terrell County
Solar
40.0 MWWithdrawn / abandoned Terrell, GASoutheast Nov 2016
Page 8 of 11

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)