Battery storage project IC-1155, Chatham County

Battery storage project IC-1155, Chatham County is a 50.0 MW battery storage request withdrawn in the Southeast interconnection queue, in Chatham County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-1155
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Cherokee - Grange Road 46 kV Line
Location
Chatham County, Georgia
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
20 July 2023
Proposed online date
September 2025
Withdrawn
September 2024

Location

Marker shows the centre of Chatham County; the queue data does not give exact sites.