United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-614, Colquitt County
Solar project IC-614, Colquitt County is a 40.0 MW solar request withdrawn in the Southeast interconnection queue, in Colquitt County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2017 (completed)
- Withdrawn / abandonedApr 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-614
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Sunset - Riverwood 46 kV Line
- Location
- Colquitt County, Georgia
- Technology
- Solar: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 22 March 2017
- Withdrawn
- April 2017
Location
Marker shows the centre of Colquitt County; the queue data does not give exact sites.
Other requests in Colquitt County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem