United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTOdom Solar (aka Peachtree Solar)
Odom Solar (aka Peachtree Solar) is a 22.0 MW solar request built and operating in the Southeast interconnection queue, in Colquitt County, Georgia, connecting to Georgia Transmission.
Request details
- Queue ID
- GI-082
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- East Berlin 230 kV Sub
- Location
- Colquitt County, Georgia
- Technology
- Solar: 22.0 MW
- Total requested
- 22.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 31 December 2023
Location
Marker shows the centre of Colquitt County; the queue data does not give exact sites.
Other requests in Colquitt County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem