United States βΊ Grid βΊ Interconnection queues βΊ Georgia
OTHER Β· SOUTHEASTOther project IC-246, Troup County
Other project IC-246, Troup County is a 55.0 MW other request withdrawn in the Southeast interconnection queue, in Troup County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2011 (completed)
- Withdrawn / abandonedNov 2012 (project stopped here)
- ConsentedNov 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-246
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Kia Motors - Lagrange #11 115 kV Line
- Location
- Troup County, Georgia
- Technology
- Other: 55.0 MW
- Total requested
- 55.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 27 January 2011
- Agreement signed
- 28 November 2011
- Withdrawn
- November 2012
Location
Marker shows the centre of Troup County; the queue data does not give exact sites.
Other requests in Troup County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem