SOLAR Β· SOUTHEAST

Solar project IC-625, Bulloch County

Solar project IC-625, Bulloch County is a 58.8 MW solar request withdrawn in the Southeast interconnection queue, in Bulloch County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-625
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Claxton - Statesboro Primary 115 kV Line
Location
Bulloch County, Georgia
Technology
Solar: 58.8 MW
Total requested
58.8 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
20 April 2017
Withdrawn
May 2023

Location

Marker shows the centre of Bulloch County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Bulloch County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem