OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 74

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 74 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 822, Sanpete County
Solar · PacifiCorp Energy Supply Management
30.0 MWWithdrawn / abandoned Sanpete, UTWest Nov 2016target 2018
Solar + storage project Company OC, Lander County
Solar + storage
30.0 MWWithdrawn / abandoned Lander, NVWest Sep 2022target 2026
Geothermal project G0493, Cassia County
Geothermal
30.0 MWWithdrawn / abandoned Cassia, IDWest Aug 2013target 2016
Solar project Q109, Maricopa County
Solar
30.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Battery storage project 382, Gallatin County
Battery storage
30.0 MWWithdrawn / abandoned Gallatin, MTWest Jun 2020target 2023
30MW Walla Walla-Pendleton
Onshore wind · FPL Energy Power Marketing Inc
30.0 MWWithdrawn / abandoned Umatilla, ORWest Jun 2001target 2002
Other project Q571, Navajo County
Other
30.0 MWWithdrawn / abandoned Navajo, AZWest May 2024target 2027
Battery storage project 386, Gallatin County
Battery storage
30.0 MWWithdrawn / abandoned Gallatin, MTWest Jun 2020target 2023
Solar project G0623, Lake County
Solar
30.0 MWWithdrawn / abandoned Lake, ORWest May 2019target 2021
Onshore wind project GI-0120, Lamoure County
Onshore wind
30.0 MWWithdrawn / abandoned Lamoure, NDWest Dec 2001
Other project 35, Payette County
Other
28.0 MWWithdrawn / abandoned Payette, IDWest May 2001target 2001
Other project 32, Cassia County
Other
28.0 MWWithdrawn / abandoned Cassia, IDWest May 2001target 2001
Other project 31, Minidoka County
Other
28.0 MWWithdrawn / abandoned Minidoka, IDWest May 2001target 2001
Other project 36, Gooding County
Other
28.0 MWWithdrawn / abandoned Gooding, IDWest May 2001target 2002
Other project 44, Cassia County
Other
28.0 MWWithdrawn / abandoned Cassia, IDWest May 2001target 2001
Other project 39, Gooding County
Other
28.0 MWWithdrawn / abandoned Gooding, IDWest May 2001target 2002
Geothermal project 231-A, Beaver County
Geothermal
28.0 MWWithdrawn / abandoned Beaver, UTWest Jun 2008target 2008
Other project 29, Twin Falls County
Other
28.0 MWWithdrawn / abandoned Twin Falls, IDWest May 2001target 2001
Other project 38, Jerome County
Other
28.0 MWWithdrawn / abandoned Jerome, IDWest May 2001target 2001
Other project G0394, Deschutes County
Other
28.0 MWWithdrawn / abandoned Deschutes, ORWest Nov 2009target 2012
Other project 45, Ada County
Other
28.0 MWWithdrawn / abandoned Ada, IDWest May 2001target 2001
Other project 34, Cassia County
Other
28.0 MWWithdrawn / abandoned Cassia, IDWest May 2001target 2001
Other project 30, Minidoka County
Other
28.0 MWWithdrawn / abandoned Minidoka, IDWest May 2001target 2001
Other project 28, Minidoka County
Other
28.0 MWWithdrawn / abandoned Minidoka, IDWest May 2001target 2001
Other project 33, Cassia County
Other
28.0 MWWithdrawn / abandoned Cassia, IDWest May 2001target 2001
Other project 37, Gooding County
Other
28.0 MWWithdrawn / abandoned Gooding, IDWest May 2001target 2002
Other project 27, Jerome County
Other
28.0 MWWithdrawn / abandoned Jerome, IDWest May 2001target 2001
Solar project 126, Cochise County
Solar
28.0 MWWithdrawn / abandoned Cochise, AZWest Jun 2022target 2024
Onshore wind project 861, Carbon County
Onshore wind
27.5 MWWithdrawn / abandoned Carbon, WYWest Apr 2017target 2019
Geothermal project 393, Lake County
Geothermal
27.0 MWWithdrawn / abandoned Lake, ORWest Jul 2011
Other project 3, King County
Other
27.0 MWWithdrawn / abandoned King, WAWest May 2005target 2007
Solar project Q245, Yavapai County
Solar
26.0 MWWithdrawn / abandoned Yavapai, AZWest Jun 2016target 2018
Solar project 2015-G1, Merced County
Solar
26.0 MWWithdrawn / abandoned Merced, CAWest Jan 2015target 2020
Onshore wind project 858, Carbon County
Onshore wind
26.0 MWWithdrawn / abandoned Carbon, WYWest Apr 2017target 2020
Other project 319, Lake County
Other
26.0 MWWithdrawn / abandoned Lake, ORWest Feb 2010
Solar project 345, Yellowstone County
Solar
25.9 MWWithdrawn / abandoned Yellowstone, MTWest Jun 2018target 2020
Solar project 466, Iron County
Solar
25.6 MWWithdrawn / abandoned Iron, UTWest Feb 2013target 2014
Solar project 467, Utah County
Solar
25.6 MWWithdrawn / abandoned Utah, UTWest Feb 2013target 2015
Gas project 1079, Sweetwater County
Gas
25.5 MWWithdrawn / abandoned Sweetwater, WYWest Oct 2018target 2019
Hydro project 237-A, Skamania County
Hydro · PacifiCorp Commercial & Trading
25.0 MWWithdrawn / abandoned Skamania, WAWest Jul 2008
Onshore wind project 210, Judith Basin County
Onshore wind
25.0 MWWithdrawn / abandoned Judith Basin, MTWest Aug 2015target 2016
Hydro project 237-B, Skamania County
Hydro · PacifiCorp Commercial & Trading
25.0 MWWithdrawn / abandoned Skamania, WAWest Jul 2008
Geothermal project Company MP, Churchill County
Geothermal
25.0 MWWithdrawn / abandoned Churchill, NVWest Mar 2022target 2022
Geothermal project Company HC, Mineral County
Geothermal
25.0 MWWithdrawn / abandoned Mineral, NVWest Mar 2016target 2018
JP Saylor and Associates
Onshore wind · J P Saylor & Associates
25.0 MWWithdrawn / abandoned Curry, ORWest Dec 2000target 2001
Onshore wind project 209, Sweet Grass County
Onshore wind
25.0 MWWithdrawn / abandoned Sweet Grass, MTWest Aug 2015target 2016
Onshore wind project 171, Judith Basin County
Onshore wind
25.0 MWWithdrawn / abandoned Judith Basin, MTWest Jul 2014target 2015
Solar + storage project C4-113, Jefferson County
Solar + storage
25.0 MWWithdrawn / abandoned Jefferson, ORWest May 2024target 2026
Solar project Q187, Maricopa County
Solar
25.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2011target 2012
Solar project Q177, Maricopa County
Solar
25.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2013
Page 74 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)