πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR Β· WEST

Solar project Q177, Maricopa County

Solar project Q177, Maricopa County is a 25.0 MW solar request withdrawn in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q177
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Baseline 69 kV Substation
Location
Maricopa County, Arizona
Technology
Solar: 25.0 MW
Total requested
25.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
11 January 2011
Proposed online date
December 2013

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem