GEOTHERMAL Β· WEST

Geothermal project G0493, Cassia County

Geothermal project G0493, Cassia County is a 30.0 MW geothermal request withdrawn in the West interconnection queue, in Cassia County, Idaho.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0493
Grid region
West (non-ISO utilities)
Connection point (POI)
At or near BPA's Bridge Substation.
Location
Cassia County, Idaho
Technology
Geothermal: 30.0 MW
Total requested
30.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
6 August 2013
Proposed online date
January 2016

Location

Marker shows the centre of Cassia County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Cassia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem