United States βΊ Grid βΊ Interconnection queues βΊ Idaho
GEOTHERMAL Β· WESTGeothermal project G0493, Cassia County
Geothermal project G0493, Cassia County is a 30.0 MW geothermal request withdrawn in the West interconnection queue, in Cassia County, Idaho.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G0493
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- At or near BPA's Bridge Substation.
- Location
- Cassia County, Idaho
- Technology
- Geothermal: 30.0 MW
- Total requested
- 30.0 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 6 August 2013
- Proposed online date
- January 2016
Location
Marker shows the centre of Cassia County; the queue data does not give exact sites.
Other requests in Cassia County
- Onshore wind project 157, Cassia CountyOnshore wind Β· 19.9 MW Β· built
- Geothermal project hist_q51, Cassia CountyGeothermal Β· 13.0 MW Β· built
- Onshore wind project 155, Cassia CountyOnshore wind Β· 11.6 MW Β· built
- Onshore wind project 301, Cassia CountyOnshore wind Β· 10.8 MW Β· built
- Onshore wind project 105, Cassia CountyOnshore wind Β· 10.5 MW Β· built
- Other project 501, Cassia CountyOther Β· 5.0 MW Β· built
- Onshore wind project 299, Cassia CountyOnshore wind Β· 1.2 MW Β· built
- Onshore wind project 121, Cassia CountyOnshore wind Β· 240 MW Β· withdrawn
- Windland IncOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project 302, Cassia CountyOnshore wind Β· 148 MW Β· withdrawn
- Geothermal project G0497, Cassia CountyGeothermal Β· 45.0 MW Β· withdrawn
- USGeothermalGeothermal Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem