United States › Grid › Interconnection queues › Idaho

ONSHORE WIND · WEST

Onshore wind project 105, Cassia County

Onshore wind project 105, Cassia County is a 10.5 MW onshore wind request built and operating in the West interconnection queue, in Cassia County, Idaho, connecting to Idaho Power Company.

Queue statusOperating
  1. PlanningQueued Mar 2004 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
105
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
34.5kV
Location
Cassia County, Idaho
Technology
Wind: 10.5 MW
Total requested
10.5 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
18 March 2004
Proposed online date
December 2010
Came online
December 2010

Location

Marker shows the centre of Cassia County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Cassia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem