United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 66

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 66 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project X3-034, Washington County
Solar
20.0 MWWithdrawn / abandoned Washington, PAPJM Aug 2011target 2012
Solar project W2-097, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Jul 2010target 2012
Parnell Solar
Solar · Parnell Solar, LLC
20.0 MWWithdrawn / abandoned Martin, NCPJM Sep 2020target 2023
Solar project AG2-337, Henry County
Solar · Reserve Energy Exploration Company
20.0 MWWithdrawn / abandoned Henry, OHPJM Mar 2021target 2023
Solar project W3-072, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2010target 2012
Solar project AF2-334, Montour County
Solar
20.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Battery storage project AG2-229, Floyd County
Battery storage
20.0 MWWithdrawn / abandoned Floyd, VAPJM Mar 2021target 2024
Culpeper North
Solar
20.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2017target 2021
Solar project AF1-284, Garrett County
Solar
20.0 MWWithdrawn / abandoned Garrett, MDPJM Sep 2019target 2021
Solar project W1-008, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2010target 2016
Battery storage project AH1-739, Dorchester County
Battery storage · Richfield Solar Energy LLC
20.0 MWWithdrawn / abandoned Dorchester, MDPJM target 2028
Solar project AB2-182, Cecil County
Solar
20.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Solar project Y2-059, Somerset County
Solar
20.0 MWWithdrawn / abandoned Somerset, MDPJM Aug 2012target 2015
Solar project AH1-281, Nelson County
Solar · Soltage KY DevCo, LLC
20.0 MWWithdrawn / abandoned Nelson, KYPJM Mar 2025target 2024
ASD Warner PA2 Solar LLC
Solar · ASD Warner PA2 Solar LLC
20.0 MWWithdrawn / abandoned Tioga, PAPJM Aug 2021target 2023
Solar project V2-018, Cape May County
Solar
20.0 MWWithdrawn / abandoned Cape May, NJPJM Jun 2009target 2010
Solar project V3-061, Northampton County
Solar
20.0 MWWithdrawn / abandoned Northampton, VAPJM Oct 2009target 2011
Solar project AG1-395, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2020target 2022
Solar project AG2-410, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Mar 2021target 2023
Bradley Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Gas project AH1-708, Adams County
Gas · Hunterstown Generation, LLC
20.0 MWWithdrawn / abandoned Adams, PAPJM target 2025
Solar project X1-058A_DK2, Butler County
Solar
20.0 MWWithdrawn / abandoned Butler, OHPJM Apr 2011target 2012
Solar project AG2-607, King And Queen County
Solar · Cauthornville PV I, LLC
20.0 MWWithdrawn / abandoned King And Queen, VAPJM Mar 2021target 2023
Solar project AE1-038, Kent County
Solar
20.0 MWWithdrawn / abandoned Kent, DEPJM Jun 2018target 2020
Solar project AE2-108, Hanover County
Solar
20.0 MWWithdrawn / abandoned Hanover, VAPJM Feb 2019target 2020
Crawford Solar II
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2027
Battery storage project T170, Harford County
Battery storage
20.0 MWWithdrawn / abandoned Harford, MDPJM Jan 2008target 2009
Solar project AC2-148, Lee County
Solar
20.0 MWWithdrawn / abandoned Lee, ILPJM Mar 2017target 2019
Solar project AF1-289, Bedford County
Solar
20.0 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2021
Solar project AG1-073, Caroline County
Solar
20.0 MWWithdrawn / abandoned Caroline, VAPJM Jul 2020target 2022
Solar project X4-002, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Nov 2011target 2012
Brookview Solar I
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Feb 2017target 2023
Solar project AH1-523, Lebanon County
Solar
20.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2021target 2024
Solar project W2-099, Worcester County
Solar
20.0 MWWithdrawn / abandoned Worcester, MDPJM Jul 2010target 2012
Strinestown Solar and BESS
Battery storage
20.0 MWWithdrawn / abandoned York, PAPJM Jul 2020target 2026
Battery storage project T172, Baltimore County
Battery storage
20.0 MWWithdrawn / abandoned Baltimore, MDPJM Jan 2008target 2009
Battery storage project U1-096, New Castle County
Battery storage
20.0 MWWithdrawn / abandoned New Castle, DEPJM Apr 2008target 2009
Solar project AG2-078, Washington County
Solar
20.0 MWWithdrawn / abandoned Washington, MDPJM Jan 2021target 2022
Onshore wind project Z1-074, Garrett County
Onshore wind
20.0 MWWithdrawn / abandoned Garrett, MDPJM Oct 2013target 2015
Solar + storage project AH1-412, Jefferson County
Solar + storage
20.0 MWWithdrawn / abandoned Jefferson, WVPJM Sep 2021target 2025
Noels Creek Solar
Solar · Noels Creek Solar, LLC
20.0 MWWithdrawn / abandoned Cambria, PAPJM Mar 2025target 2022
Solar project AG1-175, Surry County
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Sep 2020target 2021
Solar project AH1-035, Washington County
Solar · Park Solar, LLC
20.0 MWWithdrawn / abandoned Washington, NCPJM Feb 2025target 2024
Battery storage project AB2-094, Hunterdon County
Battery storage
20.0 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2016target 2017
Battery storage project AF2-109, Queen Anne's County
Battery storage
20.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Feb 2020target 2022
Ex-Umphlette LLC
Solar
20.0 MWWithdrawn / abandoned Essex, VAPJM Sep 2020target 2023
Solar project AF2-239, Bradford County
Solar
20.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2021
Battery storage project AG2-535, Warren County
Battery storage · Mansfield 3 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Solar project AF1-068, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Aug 2019target 2022
Solar project X3-059, Marion County
Solar
20.0 MWWithdrawn / abandoned Marion, OHPJM Oct 2011target 2012
Page 66 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)