Solar project X3-034, Washington County

Solar project X3-034, Washington County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Washington County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedSep 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X3-034
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Hunterstown-Jackson 130kV
Location
Washington County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
31 August 2011
Proposed online date
August 2012
Withdrawn
September 2012

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.