United States › Grid › Interconnection queues › Colorado

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown36875.4 GW
Active in queue43.2 GW209 requests
Agreement signed11.0 GW60 requests
Withdrawn36875.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

368 requests · page 6 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2008-28, Saguache County
Solar
100 MWWithdrawn / abandoned Saguache, COWest Nov 2008target 2015
Solar project GI-2014-11, Alamosa County
Solar
100 MWWithdrawn / abandoned Alamosa, COWest Nov 2014target 2016
Battery storage project GI-SISS-2025-01, Kit Carson County
Battery storage
100 MWWithdrawn / abandoned Kit Carson, COWest Jun 2025target 2028
Onshore wind project GI-2014-1, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, COWest Jan 2014target 2016
Onshore wind project GI-2008-4, Baca County
Onshore wind
100 MWWithdrawn / abandoned Baca, COWest Apr 2008target 2010
Solar project GI-2008-27, Saguache County
Solar
100 MWWithdrawn / abandoned Saguache, COWest Nov 2008target 2014
Solar project GI-2020-04, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Mar 2020target 2023
Solar + storage project GI-2017-28, Pueblo County
Solar + storage
100 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Battery storage project GI-2023-3, Adams County
Battery storage
100 MWWithdrawn / abandoned Adams, COWest May 2023target 2027
Solar project GI-2016-16, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Aug 2016target 2018
Solar project GI-2008-20, Saguache County
Solar
100 MWWithdrawn / abandoned Saguache, COWest Oct 2008target 2011
Onshore wind project 17-08211, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2020
Battery storage project GI-2025-11, Mesa County
Battery storage
100 MWWithdrawn / abandoned Mesa, COWest Apr 2025target 2028
Solar + storage project GI-CS-2025-13, Weld County
Solar + storage
97.0 MWWithdrawn / abandoned Weld, COWest Sep 2025target 2028
Battery storage project GI-2021-23, Alamosa County
Battery storage
95.0 MWWithdrawn / abandoned Alamosa, COWest Oct 2021target 2025
Solar project BHCT G25, Pueblo County
Solar
95.0 MWWithdrawn / abandoned Pueblo, COWest target 2020
Gas project GI-2006-1b, Weld County
Gas
91.0 MWWithdrawn / abandoned Weld, COWest Jan 2006target 2007
Onshore wind project GI-2007-8, Baca County
Onshore wind
86.0 MWWithdrawn / abandoned Baca, COWest Jun 2007target 2011
Solar + storage project BHCT G36, Pueblo County
Solar + storage
80.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2022target 2026
Solar project GI-2018-20, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest May 2018target 2020
Solar project BHCT G30, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2021target 2024
Onshore wind project 18-07261, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Jul 2018target 2019
Solar project GI-2017-9, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2017target 2019
Onshore wind project GI-2004-8, Eagle County
Onshore wind
80.0 MWWithdrawn / abandoned Eagle, COWest Sep 2004target 2006
Onshore wind project 17-08072, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2019
Solar project GI-2016-12, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Jun 2016target 2019
Solar project GI-2018-2, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project 18-02232, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest Feb 2018target 2020
Solar project 19-09231, Larimer County
Solar
80.0 MWWithdrawn / abandoned Larimer, COWest Sep 2019target 2023
Battery storage project GI-2019-3, Pueblo County
Battery storage
75.0 MWWithdrawn / abandoned Pueblo, COWest Mar 2019target 2022
Solar project GI-2017-48, Weld County
Solar
75.0 MWWithdrawn / abandoned Weld, COWest Nov 2017target 2020
Solar project GI-2017-51, Arapahoe County
Solar
75.0 MWWithdrawn / abandoned Arapahoe, COWest Dec 2017target 2020
Solar project GI-2018-28, Pueblo County
Solar
74.9 MWWithdrawn / abandoned Pueblo, COWest Aug 2018target 2023
Solar project GI-2018-23, Park County
Solar
72.0 MWWithdrawn / abandoned Park, COWest Jul 2018target 2022
Solar project 1RSC-2020-01, Park County
Solar
72.0 MWWithdrawn / abandoned Park, COWest Feb 2020target 2022
Onshore wind project BHCT G42, Pueblo County
Onshore wind
70.0 MWWithdrawn / abandoned Pueblo, COWest Apr 2023target 2025
Onshore wind project GI-2004-10, Adams County
Onshore wind
70.0 MWWithdrawn / abandoned Adams, COWest Nov 2004target 2005
Onshore wind project GI-2004-11, Prowers County
Onshore wind
69.0 MWWithdrawn / abandoned Prowers, COWest Nov 2004target 2005
Solar project GI-TC-2024-32, Moffat County
Solar
66.5 MWWithdrawn / abandoned Moffat, COWest May 2024target 2027
Solar project BHCT G13, Pueblo County
Solar
63.0 MWWithdrawn / abandoned Pueblo, COWest Sep 2014target 2017
Solar project BHCT G20, Pueblo County
Solar · Black Hills Electric Generation LLC
60.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2015target 2022
Solar project GI-2016-1, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2016target 2018
Solar project BHCT G22, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest May 2017target 2020
Solar project GI-2014-8, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2014target 2016
Solar project GI-2011-3, Alamosa County
Solar
60.0 MWWithdrawn / abandoned Alamosa, COWest Mar 2011target 2014
Solar project BHCT-G12, Pueblo County
Solar · Black Hills Electric Generation LLC
60.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2014target 2016
Solar project GI-2014-12, Pueblo County
Solar
53.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2014target 2016
Solar project 1RSC-2020-04, Pueblo County
Solar
53.0 MWWithdrawn / abandoned Pueblo, COWest Mar 2020target 2022
Battery storage project GI-2014-6, Pueblo County
Battery storage
52.0 MWWithdrawn / abandoned Pueblo, COWest Sep 2019target 2023
Solar project GI-2023-13, Garfield County
Solar
52.0 MWWithdrawn / abandoned Garfield, COWest May 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)