πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

ONSHORE WIND Β· WEST

Onshore wind project GI-2004-10, Adams County

Onshore wind project GI-2004-10, Adams County is a 70.0 MW onshore wind request withdrawn in the West interconnection queue, in Adams County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2004 (completed)
  2. Withdrawn / abandonedOct 2005 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2004-10
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Pawnee-Daniels Park 230kV Line
Location
Adams County, Colorado
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study complete System Impact Study complete Request Withdrawn 10/14/05
Queue status
Withdrawn
Entered queue
10 November 2004
Proposed online date
December 2005
Withdrawn
October 2005

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem