πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) (2022 requests) β€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30137.9 GW
Active in queue37.9 GW301 requests
Agreement signed0.0 MW0 requests
Withdrawn18219.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

301 requests Β· page 6 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AI1-175, Marion County
Solar + storage
19.5 MWIn study Marion, OHPJM Sep 2022target 2024
Gas project AI2-020, Warren County
Gas
19.0 MWIn study Warren, VAPJM Dec 2022target 2022
Battery storage project AH2-127, Burlington County
Battery storage
18.0 MWIn study Burlington, NJPJM Feb 2022target 2023
Solar + storage project AH2-262, Frederick County
Solar + storage
17.0 MWIn study Frederick, MDPJM Mar 2022target 2026
Solar + storage project AI1-217, Centre County
Solar + storage
17.0 MWIn study Centre, PAPJM Sep 2022target 2024
Solar project AH2-105, Rockingham County
Solar
16.0 MWIn study Rockingham, VAPJM Feb 2022target 2024
Solar project AI1-173, Stephenson County
Solar
16.0 MWIn study Stephenson, ILPJM Sep 2022target 2027
Solar project AI1-077, Mchenry County
Solar
15.8 MWIn study Mchenry, ILPJM Jul 2022target 2025
Solar project AH2-119, Crawford County
Solar
15.0 MWIn study Crawford, PAPJM Feb 2022target 2025
Solar project AI1-082, Westmoreland County
Solar
15.0 MWIn study Westmoreland, PAPJM Jul 2022target 2026
Solar project AI1-139, Lorain County
Solar
14.8 MWIn study Lorain, OHPJM Sep 2022target 2025
Solar project AI1-095, Butler County
Solar
14.0 MWIn study Butler, PAPJM Aug 2022target 2026
Solar project AH2-157, Somerset County
Solar
12.0 MWIn study Somerset, PAPJM Mar 2022target 2025
Solar project AH2-189, Susquehanna County
Solar
12.0 MWIn study Susquehanna, PAPJM Mar 2022target 2025
Solar project AH2-190, Somerset County
Solar
12.0 MWIn study Somerset, PAPJM Mar 2022target 2025
Solar + storage project AH2-384, Martin County
Solar + storage
10.0 MWIn study Martin, NCPJM Mar 2022target 2026
Solar project AI1-126, Cumberland County
Solar
10.0 MWIn study Cumberland, VAPJM Sep 2022target 2024
Solar project AH2-137, Amherst County
Solar
10.0 MWIn study Amherst, VAPJM Feb 2022target 2026
Battery storage project AH2-205, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Solar project AH2-320, Cambria County
Solar
10.0 MWIn study Cambria, PAPJM Mar 2022target 2024
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Battery storage project AH2-206, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Solar + storage project AI1-106, Halifax County
Solar + storage
9.9 MWIn study Halifax, VAPJM Aug 2022target 2023
Solar + storage project AI1-114, Cambria County
Solar + storage
9.9 MWIn study Cambria, PAPJM Sep 2022target 2025
Solar + storage project AI1-115, Clearfield County
Solar + storage
9.9 MWIn study Clearfield, PAPJM Sep 2022target 2025
Solar project AI1-033, Somerset County
Solar
8.0 MWIn study Somerset, NJPJM Apr 2022target 2026
Solar project AH2-128, Clarion County
Solar
8.0 MWIn study Clarion, PAPJM Feb 2022target 2026
Solar project AH2-412, Cumberland County
Solar
7.4 MWIn study Cumberland, NJPJM Mar 2022target 2022
Other project AI1-053, Mercer County
Other
6.6 MWIn study Mercer, PAPJM Jun 2022target 2022
Solar project AH2-394, Lawrence County
Solar
6.3 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project AH2-389, Lawrence County
Solar
6.0 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project AI1-122, Sussex County
Solar
5.9 MWIn study Sussex, NJPJM Sep 2022target 2025
Solar project AI2-017, Centre County
Solar
5.0 MWIn study Centre, PAPJM Dec 2022target 2026
Solar project AH2-101, Prince Edward County
Solar
5.0 MWIn study Prince Edward, VAPJM Jan 2022target 2023
Solar project AH2-066, Jefferson County
Solar
5.0 MWIn study Jefferson, PAPJM Jan 2022target 2023
Solar project AI2-019, Franklin County
Solar
5.0 MWIn study Franklin, PAPJM Dec 2022target 2026
Solar project AI1-030, Erie County
Solar
5.0 MWIn study Erie, PAPJM Apr 2022target 2024
Solar project AH2-094, Wayne County
Solar
5.0 MWIn study Wayne, PAPJM Jan 2022target 2023
Solar project AI1-026
Solar
5.0 MWIn study PJM Apr 2022target 2023
Solar + storage project AI1-128, Centre County
Solar + storage
5.0 MWIn study Centre, PAPJM Sep 2022target 2024
Solar + storage project AI1-129, Lycoming County
Solar + storage
4.5 MWIn study Lycoming, PAPJM Sep 2022target 2024
Solar + storage project AI1-127, Dauphin County
Solar + storage
4.5 MWIn study Dauphin, PAPJM Sep 2022target 2024
Solar project AI2-018, Somerset County
Solar
4.0 MWIn study Somerset, PAPJM Dec 2022target 2026
Solar project AH2-095, Crawford County
Solar
3.3 MWIn study Crawford, PAPJM Jan 2022target 2022
Solar + storage project AH2-181, Mercer County
Solar + storage
3.0 MWIn study Mercer, PAPJM Mar 2022target 2024
Solar project AH2-071, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Jan 2022target 2023
Solar project AH2-070, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Jan 2022target 2023
Solar project AI1-020
Solar
2.0 MWIn study PJM Apr 2022target 2023
Solar + storage project AH2-252
Solar + storage
2.0 MWIn study PJM Mar 2022target 2024
Solar project AH2-109
Solar
1.5 MWIn study NJPJM Feb 2022target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)