United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2022 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22843.0 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

228 requests ยท page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 566170, Wake County
Battery storage ยท Duke Energy Progress, LLC
56.0 MWAgreement signed Wake, NCSoutheast Jun 2022target 2026
Longfellow BESS I
Solar + storage ยท CENTURY GAS PROCESSING, LLC
55.0 MWAgreement signed Pecos, TXERCOT Nov 2022target 2026
Solar project 569804, Spartanburg County
Solar
54.0 MWAgreement signed Spartanburg, SCSoutheast Jun 2022target 2028
MRG Goody Storage
Solar + storage ยท MRG Goody Solar Project LLC
52.3 MWAgreement signed Lamar, TXERCOT May 2022target 2026
Gas project GI-2022-1, Weld County
Gas
52.0 MWAgreement signed Weld, COWest Mar 2022target 2023
Isaac Solar
Solar ยท Industrial Bravo Project LLC
50.7 MWAgreement signed Matagorda, TXERCOT Nov 2022target 2026
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Solar project 519, Marshall County
Solar
50.0 MWAgreement signed Marshall, MSSoutheast Sep 2022target 2029
SS50S
Solar
50.0 MWAgreement signed El Paso, TXWest Sep 2022target 2025
Battery storage project S0012, Iron County
Battery storage ยท Granite Mountain BESS West LLC
50.0 MWAgreement signed Iron, UTWest Mar 2022target 2024
Brightside Solar Alt POI
Solar ยท Brightside Solar, LLC
50.0 MWAgreement signed Live Oak, TXERCOT May 2022target 2026
Solar project 569014, Kershaw County
Solar
48.0 MWAgreement signed Kershaw, SCSoutheast Jun 2022target 2028
Gas project C2-48, Lincoln County
Gas ยท PacifiCorp
48.0 MWAgreement signed Lincoln, WYWest May 2022target 2031
West Springfield 45 MW BESS
Battery storage
45.0 MWAgreement signed Hampden, MAISO-NE Jun 2022target 2029
Onshore wind project C2-12, Converse County
Onshore wind ยท PacifiCorp
42.0 MWAgreement signed Converse, WYWest Apr 2022target 2036
Pitts Dudik II
Solar ยท Pitts Dudik II
30.2 MWAgreement signed Hill, TXERCOT Jul 2022target 2026
Onshore wind project C2-13, Carbon County
Onshore wind ยท PacifiCorp
30.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Solar project 572354, Cherokee County
Solar
28.3 MWAgreement signed Cherokee, SCSoutheast Jun 2022target 2027
Onshore wind project C2-14, Carbon County
Onshore wind ยท PacifiCorp
28.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project C2-11, Carbon County
Onshore wind ยท PacifiCorp
26.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024
Solar project BHBE G22, Meade County
Solar
20.0 MWAgreement signed Meade, SDWest Oct 2022target 2024
Battery storage project 634, Owyhee County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
13.0 MWAgreement signed Owyhee, IDWest Jan 2022target 2024
Laureles BESS
Battery storage ยท Regis Laureles LLC
9.9 MWAgreement signed Cameron, TXERCOT Oct 2022target 2025
Utopia BESS
Battery storage ยท Regis Utopia, LLC
9.8 MWAgreement signed Bandera, TXERCOT Nov 2022target 2026
Medina Lake BESS
Battery storage ยท Regis Medina Lake LLC
9.8 MWAgreement signed Bandera, TXERCOT Nov 2022target 2025
Onshore wind project C2-15, Carbon County
Onshore wind ยท PacifiCorp
6.6 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Grissom Solar
Solar
5.0 MWAgreement signed Sullivan, NHISO-NE Mar 2022target 2026
Page 5 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)