United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTBrightside Solar Alt POI
Brightside Solar Alt POI is a 50.0 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Live Oak County, Texas.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0487
- Grid region
- ERCOT (Texas)
- Developer
- Brightside Solar, LLC
- Connection point (POI)
- 8156 Charter Substation 138kV
- Location
- Live Oak County, Texas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- SS Completed, FIS Not Started, IA
- Queue status
- Active
- Entered queue
- 16 May 2022
- Proposed online date
- August 2026
Location
Marker shows the centre of Live Oak County; the queue data does not give exact sites.
Other requests in Live Oak County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem