BATTERY STORAGE · ERCOT

Medina Lake BESS

Medina Lake BESS is a 9.8 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bandera County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0499
Grid region
ERCOT (Texas)
Developer
Regis Medina Lake LLC
Connection point (POI)
Station Name (TDSP Station Code) MEDILA; Load/Load Transformer Name T2; PTI BUS number 7432; Voltage in kV (Transmission Level) 138kV
Location
Bandera County, Texas
Technology
Battery: 9.8 MW
Total requested
9.8 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
29 November 2022
Agreement signed
18 January 2023
Proposed online date
December 2025

Location

Marker shows the centre of Bandera County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bandera County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem