Requests shown23710.2 GW
Active in queue16.0 GW71 requests
Agreement signed1,225 MW24 requests
Withdrawn88792.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

237 requests · page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Mantua Creek Frequency Regularor
Battery storage
2.0 MWOperating Gloucester, NJPJM May 20112013
Princeton Hospital NRG Energy Center
Gas
2.0 MWOperating Mercer, NJPJM Feb 20152017
Cape May County Municipal Utiltities Authority (CM
Other
1.9 MWOperating Cape May, NJPJM Mar 20092013
Bcua LF
Other
1.9 MWOperating Bergen, NJPJM May 20012002
Kinsley 2 Deptford Solar
Solar
1.8 MWOperating Gloucester, NJPJM Feb 20192020
Repauno Unit 1
Gas
1.7 MWOperating NJPJM Apr 20022003
Berkshire Solar
Solar
1.6 MWOperating Morris, NJPJM Mar 20172021
Pleasantville / AC LF Unit 1
Other
1.5 MWOperating Atlantic, NJPJM Sep 20032005
Bergen 13kV
Solar
1.5 MWOperating Bergen, NJPJM Aug 20172019
Bayonne SP
Solar
1.4 MWOperating Hudson, NJPJM Apr 20102011
Durban Ave Solar
Solar
1.3 MWOperating Sussex, NJPJM Aug 20182020
Highland Park
Solar + storage
1.1 MWOperating Middlesex, NJPJM Jun 20182019
Hopewell Valley Solar
Solar + storage
1.0 MWOperating Mercer, NJPJM Feb 20152015
Lawnside Battery
Battery storage
1.0 MWOperating Camden, NJPJM Oct 20132015
Bcua LF
Other
1.0 MWOperating Bergen, NJPJM Jan 20022002
Reeve's Station South
Solar
1.0 MWOperating Burlington, NJPJM Apr 20122013
Food Bank Solar
Solar
1.0 MWOperating Union, NJPJM Jul 20112012
Hackensack Solar Farm
Solar
1.0 MWOperating Bergen, NJPJM Apr 20112013
Southern Division Headquarters
Solar
0.9 MWOperating Burlington, NJPJM Apr 20112013
Newark I SP
Solar
0.8 MWOperating Essex, NJPJM Oct 20092011
Pilesgrove Solar
Solar
0.8 MWOperating Salem, NJPJM Mar 20192019
Gas project AB1-116, Atlantic County
Gas
0.8 MWOperating Atlantic, NJPJM Oct 20152018
Rider University
Solar
0.7 MWOperating Mercer, NJPJM Jan 20112011
Tansboro Road
Gas
0.7 MWOperating Camden, NJPJM Oct 20152018
Central SP
Solar
0.7 MWOperating Somerset, NJPJM Jun 20102011
Solar project W2-052, Middlesex County
Solar
0.6 MWOperating Middlesex, NJPJM Jul 20102011
Metro Division Headquarters
Solar
0.6 MWOperating Passaic, NJPJM Jan 20112012
Pennington 13 kV Solar
Solar + storage
0.6 MWOperating Mercer, NJPJM Dec 20162017
Great Bear Hydro
Hydro
0.5 MWOperating Warren, NJPJM Mar 20062006
Solar project Z2-056, Middlesex County
Solar
0.5 MWOperating Middlesex, NJPJM Mar 20142016
Clay ST SP
Solar
0.5 MWOperating Essex, NJPJM Oct 20092010
Freemall Fuel Cell Facility
Other
0.4 MWOperating Monmouth, NJPJM Apr 20162018
Other project R91, Burlington County
Other
0.4 MWOperating Burlington, NJPJM Jan 20072007
Cook Rd SP
Solar
0.4 MWOperating Essex, NJPJM Oct 20092010
Newark II SP
Solar
0.4 MWOperating Essex, NJPJM Oct 20092010
Cooper Solar
Solar + storage
0.4 MWOperating Camden, NJPJM Sep 20152017
Cape May County Municipal Utilities Authority Landfill
Other
0.1 MWOperating Cape May, NJPJM Apr 20142015
Page 5 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)