Pilesgrove Solar

Pilesgrove Solar is a 0.8 MW solar request built and operating in the PJM interconnection queue, in Salem County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Mar 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-272
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Woodstown 12 kV
Location
Salem County, New Jersey
Technology
Solar: 0.8 MW
Total requested
0.8 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
28 March 2019
Proposed online date
December 2019
Came online
September 2019

Location

Marker shows the centre of Salem County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Salem County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem