🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

OTHER · PJM

Other project R91, Burlington County

Other project R91, Burlington County is a 0.4 MW other request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jan 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
R91
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Columbus-NJ
Location
Burlington County, New Jersey
Technology
Other: 0.4 MW
Total requested
0.4 MW
Service type
Energy only (ERIS)
Study phase
Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 January 2007
Proposed online date
October 2008
Came online
June 2007

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem