Queue statusOperating
  1. PlanningQueued Oct 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V3-066
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Cook Road 13.8kV (Park)
Location
Essex County, New Jersey
Technology
Solar: 0.4 MW
Total requested
0.4 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
30 October 2009
Proposed online date
December 2010
Came online
November 2010

Location

Marker shows the centre of Essex County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Essex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem