United States βΊ Grid βΊ Interconnection queues βΊ New Jersey
GAS Β· PJMEssex 9
Essex 9 is a 6.0 MW gas request built and operating in the PJM interconnection queue, in Essex County, New Jersey, connecting to PSEG.
Request details
- Queue ID
- G20
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Connection point (POI)
- Essex
- Location
- Essex County, New Jersey
- Technology
- Gas: 6.0 MW
- Total requested
- 6.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 5 April 2001
- Proposed online date
- June 2003
- Came online
- June 2003
Location
Marker shows the centre of Essex County; the queue data does not give exact sites.
Power plants in New Jersey Β· Transmission lines in New Jersey
Other requests in Essex County
- Newark Energy CenterGas Β· 625 MW Β· built
- Newark Energy CenterGas Β· 45.0 MW Β· built
- Newark Energy CenterGas Β· 35.0 MW Β· built
- Rutgers GenerationGas Β· 5.0 MW Β· built
- Essex County Correctional FacilityGas Β· 3.0 MW Β· built
- West Caldwell SolarSolar + storage Β· 2.0 MW Β· built
- Newark I SPSolar Β· 0.8 MW Β· built
- Clay ST SPSolar Β· 0.5 MW Β· built
- Cook Rd SPSolar Β· 0.4 MW Β· built
- Newark II SPSolar Β· 0.4 MW Β· built
- Gas project X2-050, Essex CountyGas Β· 705 MW Β· withdrawn
- Gas project S04, Essex CountyGas Β· 633 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem