United States › Grid › Interconnection queues › New Jersey
OTHER · PJMFreemall Fuel Cell Facility
Freemall Fuel Cell Facility is a 0.4 MW other request built and operating in the PJM interconnection queue, in Monmouth County, New Jersey, connecting to JCPL.
Request details
- Queue ID
- AB2-139
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- JCPL
- Connection point (POI)
- Raceway Mall 34.5kV
- Location
- Monmouth County, New Jersey
- Technology
- Other: 0.4 MW
- Total requested
- 0.4 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 29 April 2016
- Proposed online date
- June 2017
- Came online
- February 2018
Location
Marker shows the centre of Monmouth County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Monmouth County
- Monmouth Solar 1Solar · 15.4 MW · agreement signed
- Offshore wind project AI1-001, Monmouth CountyOffshore wind · 2,100 MW · in study
- Offshore wind project AJ1-015, Monmouth CountyOffshore wind · 1,342 MW · in study
- Offshore wind project AI1-110, Monmouth CountyOffshore wind · 1,310 MW · in study
- Battery storage project AI2-068, Monmouth CountyBattery storage · 250 MW · in study
- Battery storage project AI2-069, Monmouth CountyBattery storage · 250 MW · in study
- Port Belford Solar FarmSolar · 19.3 MW · in study
- Atlantic-RedBank 34.5kV SolarSolar · 20.0 MW · built
- Plumsted Energy Storage FacilityBattery storage · 20.0 MW · built
- Tinton Falls SolarSolar · 16.9 MW · built
- Northpark Solar Farm #2Solar · 9.0 MW · built
- Northpark Solar Farm #1Solar · 8.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem