Cooper Solar

Cooper Solar is a 0.4 MW solar + storage request built and operating in the PJM interconnection queue, in Camden County, New Jersey, connecting to PSEG; PSEG.

Queue statusOperating
  1. PlanningQueued Sep 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingFeb 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB1-063
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG; PSEG
Connection point (POI)
Locust St. 13kV
Location
Camden County, New Jersey
Technology
Solar: 0.4 MW · Battery
Total requested
0.4 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
1 September 2015
Proposed online date
December 2016
Came online
February 2017

Location

Marker shows the centre of Camden County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Camden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem