Gas project AB1-116, Atlantic County

Gas project AB1-116, Atlantic County is a 0.8 MW gas request built and operating in the PJM interconnection queue, in Atlantic County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingFeb 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB1-116
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Egg Harbor Road 12kV
Location
Atlantic County, New Jersey
Technology
Gas: 0.8 MW
Total requested
0.8 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
28 October 2015
Proposed online date
December 2016
Came online
February 2018

Location

Marker shows the centre of Atlantic County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Atlantic County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem