Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 415 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AH1-630, Snyder County
Solar + storage
15.0 MWWithdrawn / abandoned Snyder, PAPJM Sep 2021target 2023
Solar project G0385, Lake County
Solar
15.0 MWWithdrawn / abandoned Lake, ORWest Oct 2009target 2011
Hydro project 111, Elmore County
Hydro
15.0 MWWithdrawn / abandoned Elmore, IDWest Aug 2004target 2007
Solar project AF2-064, Warren County
Solar
15.0 MWWithdrawn / abandoned Warren, NJPJM Jan 2020target 2020
Hosier Road Solar II
Solar
15.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Mar 2019target 2022
TWE Myrtle Solar
Solar
15.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Aug 2016target 2018
Tierra Del Sol II
Solar
15.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2012target 2014
Solar project 293-B, Weber County
Solar
15.0 MWWithdrawn / abandoned Weber, UTWest Sep 2009target 2013
Solar project IC-630, Houston County
Solar
15.0 MWWithdrawn / abandoned Houston, GASoutheast Apr 2017
Battery storage project AG1-211, Mecklenburg County
Battery storage
15.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2020target 2022
Solar project X2-007, Wayne County
Solar
15.0 MWWithdrawn / abandoned Wayne, PAPJM May 2011target 2012
Minisink Valley Solar
Solar · Minisink Valley Solar 1, LLC
15.0 MWWithdrawn / abandoned Orange, NYNYISO Aug 2020
Onshore wind project L01_CE21, Stephenson County
Onshore wind
15.0 MWWithdrawn / abandoned Stephenson, ILPJM Aug 2003target 2005
Battery storage project AH1-473, York County
Battery storage
15.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2023
Battery storage project AH1-631, Crawford County
Battery storage
15.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2021target 2023
NW-Rocky Ford Solar
Solar · NW-Rocky Ford LLC
15.0 MWWithdrawn / abandoned Nottoway, VAPJM Sep 2020target 2021
Solar
Solar
15.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Dec 2019target 2021
Orrtanna
Battery storage
15.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2020target 2027
Solar project 15376, Chester County
Solar
15.0 MWWithdrawn / abandoned Chester, SCSoutheast Oct 2018
Battery storage project J1037, Murray County
Battery storage
15.0 MWWithdrawn / abandoned Murray, MNMISO Mar 2018target 2021
Solar
Solar
15.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Nov 2018target 2021
Big Pond Solar Power Plant
Solar
15.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Solar project AH1-383, Giles County
Solar
15.0 MWWithdrawn / abandoned Giles, VAPJM Sep 2021target 2024
Gas project AF1-197, Allegheny County
Gas
15.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2019target 2019
Gas project 24, Gem County
Gas
15.0 MWWithdrawn / abandoned Gem, IDWest Apr 2001target 2001
Solar project AG1-392C, Potter County
Solar · PO-Cowburn LLC
15.0 MWWithdrawn / abandoned Potter, PAPJM Oct 2020target 2022
Gas project J3744, Mason County
Gas
15.0 MWWithdrawn / abandoned Mason, MIMISO Apr 2024target 1995
Hydro project U1-071, Allegheny County
Hydro
15.0 MWWithdrawn / abandoned Allegheny, PAPJM Apr 2008target 2015
Solar project AH1-629, York County
Solar
15.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2023
Group @ Wing Lane 624 - EMA ASO
Solar + storage
15.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2022target 2023
Solar project AF2-244, Powhatan County
Solar
15.0 MWWithdrawn / abandoned Powhatan, VAPJM Mar 2020target 2023
Gas project GEN-2012-009, Yoakum County
Gas
15.0 MWWithdrawn / abandoned Yoakum, TXSPP Mar 20122014
Battery storage project AH1-475, Crawford County
Battery storage
15.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2021target 2023
Onshore wind project GEN-2014-019, Ochiltree County
Onshore wind
15.0 MWWithdrawn / abandoned Ochiltree, TXSPP Jul 2014target 2014
Hydro project AA2-020, Garrett County
Hydro
15.0 MWWithdrawn / abandoned Garrett, MDPJM Dec 2014target 2017
Sierra View Solar III
Solar
15.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Solar project AE2-268, Middlesex County
Solar
15.0 MWWithdrawn / abandoned Middlesex, VAPJM Mar 2019target 2021
Solar project AF1-218, Somerset County
Solar
15.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2019target 2020
Solar project Company 109, Clark County
Solar
15.0 MWWithdrawn / abandoned Clark, NVWest May 2011target 2013
Battery storage project AD2-128, Fayette County
Battery storage
15.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2018target 2020
Solar project AG1-287, Halifax County
Solar
15.0 MWWithdrawn / abandoned Halifax, VAPJM Sep 2020target 2022
Spout Springs Solar
Solar
15.0 MWWithdrawn / abandoned Appomattox, VAPJM Sep 2017target 2021
Indeck Yuba Energy Center
Solar
15.0 MWWithdrawn / abandoned Yuba, CACAISO Sep 2010target 2012
Coso #2
Geothermal
15.0 MWWithdrawn / abandoned Inyo, CACAISO May 2008target 2010
Solar project J3759, Jasper County
Solar
15.0 MWWithdrawn / abandoned Jasper, ILMISO Apr 2024target 2027
Solar project AF2-114, Jefferson County
Solar
15.0 MWWithdrawn / abandoned Jefferson, WVPJM Feb 2020target 2022
Other project 9, Minidoka County
Other
15.0 MWWithdrawn / abandoned Minidoka, IDWest Mar 2001target 2002
Bio Verde PV - Vlot
Solar
15.0 MWWithdrawn / abandoned Madera, CACAISO Feb 2010target 2012
Solar Wind Energy Solar Farm
Solar
15.0 MWWithdrawn / abandoned Monmouth, NJPJM Nov 2010target 2014
Solar project AB2-023, Culpeper County
Solar
15.0 MWWithdrawn / abandoned Culpeper, VAPJM Feb 2016target 2017
Page 415 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)