United States βΊ Grid βΊ Interconnection queues βΊ Michigan
GAS Β· MISOGas project J3744, Mason County
Gas project J3744, Mason County is a 15.0 MW gas request withdrawn in the MISO interconnection queue, in Mason County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3744
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- MICHIGAN POWER - PEREMARQUETTE 138.0kV
- Location
- Mason County, Michigan
- Technology
- Gas: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 18 April 2024
- Proposed online date
- October 1995
- Withdrawn
- December 2025
Location
Marker shows the centre of Mason County; the queue data does not give exact sites.
Other requests in Mason County
- Battery storage project J230, Mason CountyBattery storage Β· 70.0 MW Β· agreement signed
- Battery storage project J4093, Mason CountyBattery storage Β· 400 MW Β· in study
- Solar project J3282, Mason CountySolar Β· 297 MW Β· in study
- Solar project J2668, Mason CountySolar Β· 225 MW Β· in study
- Solar project J2670, Mason CountySolar Β· 223 MW Β· in study
- Solar project J2669, Mason CountySolar Β· 140 MW Β· in study
- Battery storage project J3007, Mason CountyBattery storage Β· 100 MW Β· in study
- Battery storage project J2392, Mason CountyBattery storage Β· 100 MW Β· in study
- Battery storage project J229, Mason CountyBattery storage Β· 70.0 MW Β· built
- Battery storage project J228, Mason CountyBattery storage Β· 70.0 MW Β· built
- Battery storage project J231, Mason CountyBattery storage Β· 70.0 MW Β· built
- Battery storage project J227, Mason CountyBattery storage Β· 70.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem