Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 4 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G1009, Yakima County
Battery storage
600 MWWithdrawn / abandoned Yakima, WAWest Nov 2023target 2027
Solar + storage project Company 236, Nye County
Solar + storage
600 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Solar + storage project GEN-2022-209, Andrew County
Solar + storage
600 MWWithdrawn / abandoned Andrew, MOSPP Mar 2023target 2027
Solar + storage project Company 245, Nye County
Solar + storage
600 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2030
Solar + storage project Q110, Navajo County
Solar + storage
600 MWWithdrawn / abandoned Navajo, AZWest Sep 2023target 2027
Solar + storage project G1061, Jefferson County
Solar + storage
600 MWWithdrawn / abandoned Jefferson, ORWest Dec 2023target 2029
Liberty BESS
Battery storage ยท North Bergen Liberty Generating
600 MWWithdrawn / abandoned Hudson, NJNYISO May 2023
Solar + storage project C3-180, Morrow County
Solar + storage
600 MWWithdrawn / abandoned Morrow, ORWest May 2023target 2026
Wind + storage project C3-025, Carbon County
Wind + storage
600 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2027
Other project 154, Cochise County
Other
600 MWWithdrawn / abandoned Cochise, AZWest Apr 2023target 2027
Solar + storage project PIS044, Morrow County
Solar + storage
600 MWWithdrawn / abandoned Morrow, ORWest Jun 2023target 2026
Solar + storage project G0939, Gilliam County
Solar + storage
600 MWWithdrawn / abandoned Gilliam, ORWest Sep 2023target 2027
Scorpio Storage
Battery storage
600 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar + storage project 22-119, Lake County
Solar + storage
600 MWWithdrawn / abandoned Lake, ORWest Jan 2023target 2026
Golden Bear
Solar + storage
594 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
La Luz Energy Center
Solar + storage
588 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Spectrum Energy Storage 2
Battery storage
566 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Campito Peak
Battery storage
566 MWWithdrawn / abandoned Inyo, CACAISO Apr 2023target 2031
Reed Meadow
Battery storage
566 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2031
Monte Cristo Solar 1
Solar
553 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Monte Cristo Solar 2
Solar
553 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Solar + storage project Company OG, Lander County
Solar + storage
550 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar project GEN-2023-240, Bailey County
Solar
550 MWWithdrawn / abandoned Bailey, TXSPP Oct 2023target 2030
Solar + storage project Company 234, Nye County
Solar + storage
540 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Chuckwalla
Solar + storage
535 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Apis Solar
Solar ยท S&S Renewables LLC
534 MWWithdrawn / abandoned Bee, TXERCOT Jul 2023target 2026
Titus Canyon
Solar + storage
533 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project G1022, Cowlitz County
Onshore wind
530 MWWithdrawn / abandoned Cowlitz, WAWest Nov 2023target 2030
Onshore wind project G1021, Cowlitz County
Onshore wind
530 MWWithdrawn / abandoned Cowlitz, WAWest Nov 2023target 2028
Wind + storage project 726, Owyhee County
Wind + storage
529 MWWithdrawn / abandoned Owyhee, IDWest Jun 2023target 2027
Battery Storage
Battery storage
529 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2023target 2028
Crossover
Solar + storage
528 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
West Wonder Solar
Solar + storage
525 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Musketeers Solar 1
Solar + storage
525 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Sorrento
Solar + storage
525 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Lockhart 4 Energy Storage
Battery storage
520 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Baca Solar
Battery storage
520 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Cedro
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Carranza
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Palmera
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Vegas Valley
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Midas Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Temescal Canyon Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Frates Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Vulcan Tertius
Solar + storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Fritts
Solar + storage
517 MWWithdrawn / abandoned Fresno, CACAISO Apr 2023target 2029
Victorious
Battery storage
516 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2023target 2028
Bellhop
Battery storage
516 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Olympic
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Stocker Storage
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)