BATTERY STORAGE Β· NYISO

Liberty BESS

Liberty BESS is a 600 MW battery storage request withdrawn in the NYISO interconnection queue, in Hudson County, New Jersey, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1556
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
North Bergen Liberty Generating
Connection point (POI)
W49th St 345kV substation
Location
Hudson County, New Jersey
Technology
Battery: 600 MW
Total requested
600 MW
Queue status
Withdrawn
Entered queue
12 May 2023

Location

Marker shows the centre of Hudson County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Hudson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem