Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 142, Canyon County Gas |
200 MW | Withdrawn / abandoned |
| Solar + storage project 1190, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 700, Ada County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C3-109, Caribou County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 102, Latah County Solar + storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project 182, Owyhee County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar + storage project 699, Ada County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 683, Ada County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project 623, Bingham County Solar · Mosby Butte Solar, LLC |
200 MW | Withdrawn / abandoned |
| Battery storage project 117, Kootenai County Battery storage |
200 MW | Withdrawn / abandoned |
| Gas project 109, Kootenai County Gas |
200 MW | Withdrawn / abandoned |
| Gas project 144, Ada County Gas |
200 MW | Withdrawn / abandoned |
| Solar + storage project 631, Butte County Solar + storage |
200 MW | Withdrawn / abandoned |
| Battery storage project C3-173, Jefferson County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 649, Ada County Solar + storage |
200 MW | Withdrawn / abandoned |
| Battery storage project TCS-17, Kootenai County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project C3-051, Franklin County Battery storage · PacifiCorp |
200 MW | Withdrawn / abandoned |
| Solar + storage project TCS-50, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project 257, Twin Falls County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar + storage project 1201, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Battery storage project T2-016, Owyhee County Battery storage · PacifiCorp |
200 MW | Withdrawn / abandoned |
| Battery storage project PIS080, Owyhee County Battery storage · PacifiCorp |
200 MW | Withdrawn / abandoned |
| Battery storage project C3-007, Owyhee County Battery storage · PacifiCorp |
200 MW | Withdrawn / abandoned |
| Battery storage project C4-061, Owyhee County Battery storage · PacifiCorp |
200 MW | Withdrawn / abandoned |
| Solar + storage project C3-183, Bingham County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 769, Minidoka County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C3-099, Caribou County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C3-037, Bannock County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar project C3-155, Bingham County Solar · PacifiCorp |
199 MW | Withdrawn / abandoned |
| Solar + storage project C2-60, Jefferson County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C2-123, Jefferson County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C2-76, Bingham County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar project C3-154, Bingham County Solar · PacifiCorp |
199 MW | Withdrawn / abandoned |
| Solar project C3-153, Bingham County Solar · PacifiCorp |
199 MW | Withdrawn / abandoned |
| Solar + storage project C3-159, Jefferson County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar project C4-090, Bonneville County Solar |
199 MW | Withdrawn / abandoned |
| Solar + storage project 791, Owyhee County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C1-21, Caribou County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar project C4-091, Bonneville County Solar |
199 MW | Withdrawn / abandoned |
| Battery storage project C3-100, Bannock County Battery storage |
199 MW | Withdrawn / abandoned |
| Gas project 138, Elmore County Gas |
196 MW | Withdrawn / abandoned |
| Onshore wind project 398-A, Bonneville County Onshore wind |
192 MW | Withdrawn / abandoned |
| Battery storage project 778, Owyhee County Battery storage |
190 MW | Withdrawn / abandoned |
| Battery storage project 697, Power County Battery storage |
180 MW | Withdrawn / abandoned |
| Battery storage project 698, Canyon County Battery storage |
180 MW | Withdrawn / abandoned |
| Battery storage project 652, Minidoka County Battery storage |
180 MW | Withdrawn / abandoned |
| Battery storage project C3-168, Owyhee County Battery storage |
175 MW | Withdrawn / abandoned |
| Battery storage project C4-116, Owyhee County Battery storage |
175 MW | Withdrawn / abandoned |
| Solar project G1033, Fremont County Solar |
170 MW | Withdrawn / abandoned |
| Onshore wind project 294, Power County Onshore wind |
160 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)