πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

SOLAR + STORAGE Β· WEST

Solar + storage project C2-76, Bingham County

Solar + storage project C2-76, Bingham County is a 199 MW solar + storage request withdrawn in the West interconnection queue, in Bingham County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-76
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Goshen substation
Location
Bingham County, Idaho
Technology
Solar: 199 MW Β· Battery
Total requested
199 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
11 May 2022
Proposed online date
December 2027

Location

Marker shows the centre of Bingham County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Bingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem