πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

SOLAR + STORAGE Β· WEST

Solar + storage project 631, Butte County

Solar + storage project 631, Butte County is a 200 MW solar + storage request withdrawn in the West interconnection queue, in Butte County, Idaho, connecting to Idaho Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
631
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
Antelope 230kV Substation
Location
Butte County, Idaho
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 January 2022

Location

Marker shows the centre of Butte County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Butte County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem