Onshore wind project 182, Owyhee County

Onshore wind project 182, Owyhee County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Owyhee County, Idaho, connecting to Idaho Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
182
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
tbd
Location
Owyhee County, Idaho
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
17 October 2006
Proposed online date
September 2008

Location

Marker shows the centre of Owyhee County; the queue data does not give exact sites.