BATTERY STORAGE Β· WEST

Battery storage project 697, Power County

Battery storage project 697, Power County is a 180 MW battery storage request withdrawn in the West interconnection queue, in Power County, Idaho, connecting to Idaho Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
697
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
Kinport 138kV Substation
Location
Power County, Idaho
Technology
Battery: 180 MW
Total requested
180 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
28 December 2022
Proposed online date
June 2026

Location

Marker shows the centre of Power County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Power County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem