United States › Grid › Interconnection queues › California
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in California — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Saloon Energy Storage Battery storage |
150 MW | Agreement signed |
| Sandstorm Wind Power Wind + storage |
150 MW | Agreement signed |
| Segs Expansion 2 Hybrid Solar + storage |
145 MW | Agreement signed |
| Jasmine Solar + storage |
141 MW | Agreement signed |
| Alta Vista Suntower Generating Station Solar + storage |
132 MW | Agreement signed |
| Montezuma II Wind + storage |
132 MW | Agreement signed |
| Leconte Energy Storage Battery storage |
125 MW | Agreement signed |
| Baldy Mesa 2 Solar + storage |
125 MW | Agreement signed |
| Ajo Power Bank Battery storage |
124 MW | Agreement signed |
| Los Esteros Critical Energy Facility Expansion Gas |
123 MW | Agreement signed |
| Excelsior Solar (Fka: Burford Five Points) Solar + storage |
120 MW | Agreement signed |
| Gonzaga Hybrid Wind + storage |
115 MW | Agreement signed |
| Reclaimed Wind Battery storage |
114 MW | Agreement signed |
| Serena Storage Battery storage |
114 MW | Agreement signed |
| Mulqueeney Ranch Wind Onshore wind |
114 MW | Agreement signed |
| Oakdale Storage Battery storage |
103 MW | Agreement signed |
| Los Nietos Battery storage |
102 MW | Agreement signed |
| Denali Energy Storage Battery storage |
102 MW | Agreement signed |
| Kyan Solar Solar |
102 MW | Agreement signed |
| Tokay Storage Battery storage |
102 MW | Agreement signed |
| Double Springs Energy Storage Battery storage |
101 MW | Agreement signed |
| Sunbeam Storage Battery storage |
101 MW | Agreement signed |
| Peaceful Hollow BESS Battery storage |
100 MW | Agreement signed |
| Keyhole Wind Onshore wind |
100 MW | Agreement signed |
| Golden Fields Solar Battery storage |
100 MW | Agreement signed |
| Sanborn Hybrid 4 Solar + storage |
100 MW | Agreement signed |
| Azalea Solar + storage |
99.3 MW | Agreement signed |
| Noosa Energy Storage Battery storage |
99.0 MW | Agreement signed |
| Solano 4 Wind Onshore wind |
92.4 MW | Agreement signed |
| Chalan Solar Solar + storage |
91.8 MW | Agreement signed |
| Fresno Cogeneration Expansion Project Gas |
91.8 MW | Agreement signed |
| Redwood Solar Farm Solar |
90.0 MW | Agreement signed |
| Sand Hill C Onshore wind |
84.3 MW | Agreement signed |
| Gonzaga Wind Farm Onshore wind |
80.0 MW | Agreement signed |
| Montezuma (High Winds III) Wind + storage |
76.0 MW | Agreement signed |
| Hummingbird Energy Storage Battery storage |
75.0 MW | Agreement signed |
| Willow Springs Solar 4 Battery storage |
75.0 MW | Agreement signed |
| Rosemary Solar + storage |
72.3 MW | Agreement signed |
| Fallbrook Energy Storage Battery storage |
69.6 MW | Agreement signed |
| Mulqueeney Ranch Wind 2 Onshore wind |
62.5 MW | Agreement signed |
| Angela Solar + storage |
60.0 MW | Agreement signed |
| Camino Solar Solar + storage |
58.3 MW | Agreement signed |
| Bottle Rock Power Other |
56.9 MW | Agreement signed |
| Orleans Solar + storage |
51.1 MW | Agreement signed |
| Ventasso Energy Storage Battery storage |
50.8 MW | Agreement signed |
| Willow Springs Solar 3 Battery storage |
50.0 MW | Agreement signed |
| Solar Star 4 Solar + storage |
50.0 MW | Agreement signed |
| North Johnson Energy Center Battery storage |
50.0 MW | Agreement signed |
| Chula Vista Energy Center 2 Battery storage |
50.0 MW | Agreement signed |
| Solar Star 3 Solar + storage |
50.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)