United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 378

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 378 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AB1-074, Philadelphia County
Battery storage
20.0 MWWithdrawn / abandoned Philadelphia, PAPJM Sep 2015target 2016
Champlain Solar
Solar · EDF Renewables Development, Inc.
20.0 MWWithdrawn / abandoned Clinton, NYNYISO Jun 2018
Niagara Grid I
Battery storage · Niagara Grid I, LLC
20.0 MWWithdrawn / abandoned Erie, NYNYISO Nov 2019
Woodruff Solar
Solar · Woodruff Solar, LLC
20.0 MWWithdrawn / abandoned Livingston, NYNYISO Feb 2017
Solar project AG2-588, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2021target 2024
Onshore wind project G637, Traverse County
Onshore wind
20.0 MWWithdrawn / abandoned Traverse, MNMISO May 2006target 2007
Kasson Manteca Solar
Solar
20.0 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2013target 2018
Solar project AG1-382, Cambria County
Solar
20.0 MWWithdrawn / abandoned Cambria, PAPJM Sep 2020target 2022
Old River 2
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Aug 2009target 2014
Solar project Q128, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2011
Solar project W1-118, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project AB2-062, Orange County
Solar
20.0 MWWithdrawn / abandoned Orange, VAPJM Mar 2016target 2018
Battery storage project Q263, Pinal County
Battery storage
20.0 MWWithdrawn / abandoned Pinal, AZWest Sep 2017target 2020
Forest Glen Solar
Solar · Forest Glen Solar LLC
20.0 MWWithdrawn / abandoned Allegany, NYNYISO Sep 2017
Solar + storage project AG1-274, Charlotte County
Solar + storage · CV-Tollhouse LLC
20.0 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2022
Sun Stream
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2010target 2012
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2022target 2027
Solar project G0512, Umatilla County
Solar
20.0 MWWithdrawn / abandoned Umatilla, ORWest Aug 2015target 2016
Solar project AI2-031, Sussex County
Solar
20.0 MWWithdrawn / abandoned Sussex, VAPJM Jan 2023target 2024
Onshore wind project W3-039, Hudson County
Onshore wind
20.0 MWWithdrawn / abandoned Hudson, NJPJM Aug 2010target 2012
Solar
Solar
20.0 MWWithdrawn / abandoned Knox, MEISO-NE Jun 2024target 2028
Solar project 450, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project Q74, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Oct 2009target 2010
Solar project W4-035, Clinton County
Solar
20.0 MWWithdrawn / abandoned Clinton, OHPJM Dec 2010target 2012
Solar project W4-028, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2010target 2011
Solar project AF1-151, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Kingsolar I
Solar
20.0 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2013
Solar project AB2-164, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Apr 2016target 2018
Solar project AH1-423, Champaign County
Solar
20.0 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Charles City Solar
Solar
20.0 MWWithdrawn / abandoned VAPJM Oct 2015target 2019
Astoria Energy Storage 4
Battery storage · NRG Astoria Storage LLC
20.0 MWWithdrawn / abandoned Queens, NYNYISO May 2019
Cambria Energy
Battery storage
20.0 MWWithdrawn / abandoned Cambria, PAPJM Dec 2019target 2022
Solar project AG2-033, Auglaize County
Solar
20.0 MWWithdrawn / abandoned Auglaize, OHPJM Nov 2020target 2023
Setauket Fuel Cell
Battery storage · FourGen LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jul 2019
Solar project J862, Orleans Parish County
Solar
20.0 MWWithdrawn / abandoned Orleans Parish, LAMISO Jun 2017target 2019
Churchill Storage Solutions LLC
Battery storage · Churchill Storage Solutions LLC
20.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Feb 2025target 2023
Solar project AH1-074, Huron County
Solar
20.0 MWWithdrawn / abandoned Huron, OHPJM Jul 2021target 2024
Solar project Company RC, Washoe County
Solar
20.0 MWWithdrawn / abandoned Washoe, NVWest Mar 2025target 2026
Solar + storage project AG1-279, Luzerne County
Solar + storage · LU-Tank LLC
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2022
Solar project Q324, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2020target 2022
Battery storage project AF2-351, Kankakee County
Battery storage · Deriva Energy Solar, LLC
20.0 MWWithdrawn / abandoned Kankakee, ILPJM Mar 2020target 2023
Sunshine Four
Solar
20.0 MWWithdrawn / abandoned Los Angeles, CACAISO Jan 2010target 2011
Catoctin Furnace Solar Facility
Solar
20.0 MWWithdrawn / abandoned Frederick, MDPJM Aug 2016target 2018
Geothermal project C4-032, Iron County
Geothermal
20.0 MWWithdrawn / abandoned Iron, UTWest May 2024target 2026
Solar project Company 84, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Oct 2009target 2013
Solar project W2-101, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2017
Solar project IC-549, Blount County
Solar
20.0 MWWithdrawn / abandoned Blount, ALSoutheast Nov 2016
Onshore wind project S53, Bureau County
Onshore wind
20.0 MWWithdrawn / abandoned Bureau, ILPJM May 2007target 2008
Admiral Wind LLC
Onshore wind · Admiral Wind LLC
20.0 MWWithdrawn / abandoned Madison, NYNYISO Aug 2017
Solar project W4-100, Hunterdon County
Solar
20.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2011target 2012
Page 378 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)