United States βΊ Grid βΊ Interconnection queues βΊ Texas
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Texas (2020 requests) β page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| BRP Diran BESS Battery storage Β· BRP Diran BESS LLC |
101 MW | Agreement signed |
| BRP Musca BESS Battery storage Β· BRP Musca BESS LLC |
101 MW | In study |
| SPC Bloom BESS Battery storage Β· BRP Blue Topaz 2, LLC |
100 MW | In study |
| Big Star Storage Battery storage Β· RWE Solar Development, LLC |
80.0 MW | Agreement signed |
| Noria Storage Battery storage |
75.0 MW | Paused / redesign |
| Creekfield Storage Battery storage |
69.0 MW | Paused / redesign |
| Celeste Energy Storage Battery storage |
60.9 MW | Paused / redesign |
| Lubio Solar Solar Β· BDPU Solar Lubio LLC |
54.5 MW | Agreement signed |
| Dori BQ Solar Solar + storage Β· Sunnyside Energy, LLC |
50.4 MW | Agreement signed |
| Tain Solar Solar Β· Abei Energy Green VII LLC |
37.5 MW | In study |
| Delaware Ranch Solar Solar Β· Delaware Ranch Solar, LLC |
36.0 MW | Agreement signed |
| Ty Cooke Gas |
33.0 MW | Paused / redesign |
| Hayhurst Texas Solar Solar Β· Hayhurst Texas Solar, LLC |
24.8 MW | Agreement signed |
| Brazos Wind Repower Onshore wind Β· BRAZOS WIND VENTURES, LLC |
22.4 MW | In study |
| Hays Energy Unit 3 Repower Gas Β· HAYS ENERGY, LLC |
18.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)