Interconnection queue in West (non-ISO utilities) (2024 requests) β€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown19245.5 GW
Active in queue45.5 GW192 requests
Agreement signed1,964 MW16 requests
Withdrawn23746.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

192 requests Β· page 3 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-TC-2024-29, Kit Carson County
Onshore wind
170 MWIn study Kit Carson, COWest May 2024target 2028
Solar + storage project 2024-G4
Solar + storage
170 MWIn study West Nov 2024target 2028
Onshore wind project GI-TC-2024-11, Kit Carson County
Onshore wind
167 MWAgreement signed Kit Carson, COWest May 2024target 2027
Other project Q565, Coconino County
Other
161 MWIn study Coconino, AZWest May 2024target 2025
Gas project 465, Stillwater County
Gas
150 MWIn study Stillwater, MTWest Jun 2024target 2029
Other project CLPT G29, Laramie County
Other
150 MWIn study Laramie, WYWest May 2024target 2027
Solar + storage project GI-TC-2024-02, Lincoln County
Solar + storage
150 MWIn study Lincoln, COWest Apr 2024target 2028
Sf150SB
Solar + storage
150 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar project GI-2024-03, Adams County
Solar
150 MWIn study Adams, COWest Apr 2024target 2029
Solar + storage project GI-2024-14, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest May 2024target 2027
Gas project 464, Broadwater County
Gas
150 MWIn study Broadwater, MTWest Jun 2024target 2029
Solar + storage project GI-TC-2024-01, Lincoln County
Solar + storage
150 MWIn study Lincoln, COWest Apr 2024target 2027
Solar project GI-2024-18, Morgan County
Solar
150 MWIn study Morgan, COWest May 2024target 2027
Other project Q548, Pinal County
Other
145 MWIn study Pinal, AZWest Apr 2024target 2027
Solar project GI-TC-2024-22, Weld County
Solar
140 MWIn study Weld, COWest May 2024target 2028
Battery storage project 24-03011, Larimer County
Battery storage
130 MWIn study Larimer, COWest Mar 2024target 2027
Solar + storage project 24-240, Jefferson County
Solar + storage
130 MWIn study Jefferson, ORWest Jan 2024target 2027
Solar project PIS057, Emery County
Solar Β· PacifiCorp
125 MWIn study Emery, UTWest May 2024target 2026
Solar + storage project GI-TC-2024-21, Montezuma County
Solar + storage
125 MWIn study Montezuma, COWest May 2024target 2028
Solar + storage project 2024-G2, Shasta County
Solar + storage
125 MWIn study Shasta, CAWest Nov 2024target 2028
Battery storage project S0033, Washington County
Battery storage
122 MWIn study Washington, UTWest Dec 2024target 2027
Solar project GI-2024-10, Adams County
Solar
120 MWIn study Adams, COWest May 2024target 2027
Gas project BHBE G25, Pennington County
Gas Β· Black Hills Power Inc.
115 MWIn study Pennington, SDWest Jun 2024target 2026
Gas project CLPT G30, Laramie County
Gas Β· Black Hills Electric Generation, LLC
115 MWIn study Laramie, WYWest May 2024target 2029
Gas project CLPT G31, Laramie County
Gas Β· Cheyenne Light, Fuel & Power
115 MWIn study Laramie, WYWest May 2024target 2029
Solar + storage project GI-2024-15, Alamosa County
Solar + storage
110 MWIn study Alamosa, COWest May 2024target 2028
Battery storage project IA-PNM-2024-01, Roosevelt County
Battery storage
100 MWIn study Roosevelt, NMWest Jun 2024target 2029
Battery storage project GI-TC-2024-19, Montrose County
Battery storage
100 MWAgreement signed Montrose, COWest May 2024target 2027
Ne100B
Battery storage
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Battery storage project 455, Yellowstone County
Battery storage
100 MWIn study Yellowstone, MTWest Jan 2024target 2028
Solar + storage project GI-2024-07, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest May 2024target 2028
Battery storage project GI-TC-2024-18, Montezuma County
Battery storage
100 MWIn study Montezuma, COWest May 2024target 2027
Battery storage project 145, Whatcom County
Battery storage
100 MWIn study Whatcom, WAWest Apr 2024target 2027
Solar project GI-2024-17, Alamosa County
Solar
100 MWIn study Alamosa, COWest May 2024target 2030
Battery storage project 146, Skagit County
Battery storage
100 MWIn study Skagit, WAWest Apr 2024target 2027
Solar project BHCT G52, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jun 2024target 2026
Battery storage project Q110, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Solar project GI-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Apr 2024target 2028
Ne100S
Solar
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Battery storage project 148, King County
Battery storage
100 MWIn study King, WAWest Apr 2024target 2028
Battery storage project 24-245, Washington County
Battery storage
100 MWIn study Washington, ORWest May 2024target 2027
Battery storage project S0025, Natrona County
Battery storage
100 MWIn study Natrona, WYWest Feb 2024target 2026
AN100S
Solar
100 MWAgreement signed Luna, NMWest Mar 2024target 2027
Battery storage project 150, Skagit County
Battery storage
100 MWIn study Skagit, WAWest Apr 2024target 2027
Solar project 5RSC-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jan 2024target 2028
Battery storage project Q109, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Other project Q559, Maricopa County
Other
80.0 MWIn study Maricopa, AZWest May 2024target 2028
Battery storage project S0031, Box Elder County
Battery storage
80.0 MWIn study Box Elder, UTWest Aug 2024target 2026
Battery storage project S0034, Juab County
Battery storage
80.0 MWIn study Juab, UTWest Dec 2024target 2026
Other project Q557, Navajo County
Other
75.0 MWIn study Navajo, AZWest May 2024target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)