United States › Grid › Interconnection queues › Oregon

SOLAR + STORAGE · WEST

Solar + storage project 24-240, Jefferson County

Solar + storage project 24-240, Jefferson County is a 130 MW solar + storage request in interconnection study in the West interconnection queue, in Jefferson County, Oregon, connecting to Portland General Electric.

Queue statusIn planning
  1. PlanningQueued Jan 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24-240
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
Redmond - Round Butte 230kV
Location
Jefferson County, Oregon
Technology
Solar: 130 MW · Battery
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
29 January 2024
Proposed online date
October 2027

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem